Xantrex Technology PV100S-480 installation manual Size the cable, Size the conduit

Page 46

Planning

Step 3. Size the cable.

This example assumes that the conduit length is less than 24 inches. NEC Table 310.16 (Ninth Edition) indicates the Temperature Correction Factor for

90 °C THHN cable in a 50 °C ambient is 0.82. With a required ampacity from Step 1 above of 347 amps, it can be calculated that the required cable ampacity at 50 °C in this application is 423 amps. (347 divided by 0.82)

In this example, two cables per phase termination are used, so from NEC Table 310.16 (Ninth Edition) it is apparent that the 90 °C THHN cable must be 3/0 AWG or larger. Two each 3/0 AWG conductors at 50°C have an allowable ampacity of 450 amps (225 multiplied by 2).

Step 4. Size the conduit.

In this step, the cross sectional area of all the individual cables is first calculated. Once calculated, the total cross sectional area of the cables is determined by summing their values. In this example, 3/0 AWG, 2000 V cable is selected for the AC Phase connections:

DLO 3/0 AWG Cable:

3/0 AWG DLO, 2000V, 90 °C per Phase 3/0 AWG has an O.D. of 0.789

0.789 x 0.789 x 6 x 0.7854 = 2.93 in²

Ground Cable:

1 Each #2 AWG (per NEC Table 250.122(Ninth Edition), using 400 A Breaker)

#2 AWG has an O.D. of 0.384 for THHN and 0.565 for DLO 0.565 x 0.565 x 0.7854 = 0.250 in²

Sense/Control Wires:

8 Each #16 AWG, UL1015, THHN, Hook-up Wire #16 AWG has an O.D. of 0.096

0.096 x 0.096 x 8 x 0.7854 = 0.058 in²

Total:

2.93 + 0.250 + 0.058 = 3.238 in²

Using the "Over 2 Wires" column per NEC Chapter 9, Table 4, (Ninth Edition) indicates that the following minimum permitted conduit trade size is acceptable for the 15 wires in this exercise:

EMT = 3" Trade size IMC = 3.5" Trade size RMC = 3.5" Trade size

2–12

152315 Rev C

Image 46
Contents PV100S 100 kW Grid-Tied Photovoltaic Inverter Page PV100S 100 kW Grid-Tied Photovoltaic Inverter Date and Revision Audience PurposeScope OrganizationConventions Used Following conventions are used in this guideAbbreviations and Acronyms Related InformationPage Important Safety Instructions Safety Equipment General Safety PrecautionsPersonal Safety Wiring RequirementsSafety Operational Safety Procedures Lockout and TagInterconnection Standards Compliance De-Energize/Isolation ProcedureTo isolate the PV100S Xii Contents Schematics InstallationVerification Tables Xvi Figures Figures Introduction Description of the PV100S 1Dimensions Not to scale System Specifications Electrical SpecificationsSystem Ground Requirements Environmental Specifications 3Environmental SpecificationsMain Enclosure Door Interlock Switch Operator Interface ControlsOn/Off Switch 3On/Off SwitchCommunication Features AC and DC Disconnect SwitchesSystem Status and Fault Reporting Data LoggingCommunication Methods Universal Front Panel Control Unit UfcuPC Connection Methods 6PC Connections in the Communications EnclosurePots Access Ethernet LAN Access Planning Overview of PV100S Installation Ventilation and Serviceability Requirements PV PlanningCommunication Requirements Ground RequirementsSystem Neutral Requirements Utility Side Isolation Transformer RequirementsModel PV100S-480 Electrical Diagrams and SchematicsModel PV100S-208 Layout Options 1PV100S Layout Option a2PV100S Layout Option B Conduit Penetration 3Conduit Entry Figure Reference15 cm 12 30 cm 10.5 27 cm To calculate the proper conduit size Conductor and Conduit SizingDetermine the required cable ampacity Size the cable Size the conduitAnchoring the PV100S 29 73.7 cm 16 ¼ 40.6 cm10AC Interface/Transformer Anchor Bolt Pattern Not to Scale Installation Equipment Required UnloadingMoving the PV100S Unpacking the PV100STo move the PV100S using a forklift Removing the Pallet and Moving the PV100SMounting and Anchoring the Units To mount and anchor the PV100SOpening or Closing Access Doors To lock or unlock the front door on the main inverterTo Open Access Door To Close Access Door7Transformer Access Panels Conduit Installation To install the conduitsWiring General Overcurrent Protection Conductor TerminationWire Gauge and Torque Requirements GroundingSystem Neutral Requirements Utility Side Isolation Transformer RequirementsWiring Specific AC Connections13Tie-wraps on the AC Sense Harness 15AC Terminal Connections in the Main Inverter Enclosure 17Connecting the AC Sense Harness To connect the utility service to AC Interface Enclosure18AC Terminal Connections from the Utility PV Array Connections 19PV Array Cable Routing and TerminationsPC Communications To connect a personal computer using the Pots Connection Establishing a Pots ConnectionEstablishing Wireless Connection To connect a personal computer using the GSM Wireless modemIf connecting the PC directly to the inverter Direct Connection22Direct Connect Installation Verification Verification Procedure Summary Visual Inspection of Mechanical Connections Visual Inspection of Electrical ConnectionsCorrective Action Visual Inspection, Isolation Transformer Wye/WyePerform after initial inspection if required Schematics This page intentionally left blank Figure A-1Electrical Diagram sample Schematics Appendix a Schematics Appendix a Schematics Appendix a This page was intentionally left blank Index IX-2 Rev C Page Xantrex Technology Inc