Extron electronic 300, PVS 400, 200 manual Secure the Projector Ceiling Mount to the ceiling

Page 18

Installation — Stage One, cont’d

6.Secure the Projector Ceiling Mount to the ceiling

a.Attach the four turnbuckles to the mounting plate, one at each corner.

CDO NOT rest or lean on the mounting plate or suspended ceiling when attaching turnbuckles, tie wire, or when drilling into the ceiling

NFor safest installation, insert the turnbuckle from the outside so that it hooks inwards.

b.Mark and drill holes at 10 degrees out from vertical. Drill a fifth hole directly centered above the PCM 240 for the safety cable.

c. Install appropriate anchors or lag eye-bolts for the structural ceiling into each drilled hole

d.Cut four equal lengths of the supplied hanging wire, and loop the wire through the anchors or eye screws, and the turnbuckles, then twist the wire around itself at least five times tightly.

e.Hand tighten the turnbuckles, and level the plate so it just rests on the T-grid.

CThe four hanging wires should be taut, taking the full weight of the completed installation.

Do not overtighten the turnbuckles or the T‑bar assembly could be lifted, making the suspended ceiling bowed and unsafe.

f.Tighten the four T-bar securing screws on the PCM 240.

CDO NOT rest or lean on the plate or suspended ceiling grid during installation of safety cable, or during installation and wiring of electrical boxes, accessories, and projector.

6a Attach turnbuckles at the corners

6b Mark structural ceiling for lag bolt installation

PCM

T-bar

Adjust the turnbuckles to take up any slack in the hanging wire.

6e Tighten the turnbuckles

2-6 PoleVault Systems Installation • Installation — Stage 1

Image 18
Contents PoleVault Systems Consignes de Sécurité Français PrecautionsSafety Instructions English Sicherheitsanleitungen DeutschPoleVault Systems Installation Introduction IntroductionFCC Class a Notice PoleVault System installation and wiring overview Introduction, contdRoom layout Typical classroom installationPoleVault Systems Installation Introduction Planning RoomLocation of the screen and projector Example of a classroom installationIntroduction Planning, cont’d ADA overhead and side clearance requirementsExample classroom with four speaker installation Location of MediaLink Controller and Wall PlatesType and location of the speakers Introduction Inventory Overview InventoryIncluded items PoleVault System Devices and Hardware, contd PoleVault System Devices and Hardware, cont’dIntroduction Inventory Overview, cont’d PoleVault System Ceiling SpeakersOptional installation hardware Items not includedInstallation tools Installation Overview Outline of installation stepsPoleVault Systems Installation Installation Overview PCM 240 Projector Ceiling Mount Where it goes Screws up into PCMPoleVault Systems Installation Installation Stage PMP Projector Mounting Pole Mark screen location 2c Install the PMP 2d Screw the adjuster plate onto the PMP 1a Mark the screen locationVerify the image location Installation Stage One, cont’d2f Slide and lock the projector onto the adjuster plate 2e Attach the bracket to the projectorCut the ceiling tile InstallationUsing these dimensions, mark and cut a hole for 5d Screw the PMP into the mounting plate viewed from belowSecure the Projector Ceiling Mount to the ceiling Tighten the four T-bar securing screws on the PCM6e Tighten the turnbuckles Install the Screen 6g Attach the safety cable to the PCMPower outlet installation on PCM Stage Two Install the Wall Plates and MLC 104 IP This stage involves installing the devices shown belowMLC 104 IP Plus MediaLink Controller PVS 204SA switcher Cables1d Features for mud ring installation Stage Two Install the Wallplates and MLC 104 IP PlusInstall mud rings MLC 104 IP Plus mud ringProjector communication cables from Signal Cable Label colorPull cables 2c Pull the cables at each locationInstallation Stage Two, cont’d Install wall platesInstall MediaLink Controller TWire stripping lengths4a Connecting the MLC to the switcher An RS-232 cable or IR emitter cable, as 4c Connect to the LAN using a CAT 5 cableConnect the MLC to the projector with AppropriateConnections made to the MLC 104 IP Plus 4e Secure the MLC 104 IP Plus to the mud ringStage Three Install the PV SI 3C LP Ceiling Speakers PV SI 3C LP Ceiling SpeakersCut ceiling tile Installation Stage Three, cont’d Cable the speakersStereo or dual mono output using parallel speaker wiring Pole captive screw connector4c Wire the captive screw connector Dual mono output To terminate the cable, strip the end of the cableFinish speaker installation 5a Apply putty to speaker grillPVS 204SA PoleVault Switcher Stage Four Install the PMK 450 and the PVS 204SAThis stage covers installing the devices shown below PMK 450 Pole Mount KitSwitcher and projector cable overview Installation Stage Four, cont’dInstall the PMK 450 Pole Mount kit Pull the cables3c Wire the captive screw connector for the power supply Install the PVS 204SA switcherPMK 450 bottom plate and secure it using velcro 3d Set the DIP switches as desiredConnect the cables to the switcher Finish installing the Pole Mount kitBControl/power cable from the MLC 104 IP Plus PVS 204SA cable connections4d Replace projector on the adjuster plate 4c Attach and screw down rear plate1a Load Global Configurator 2 software Stage Five Configure the SystemConfigure the system Launch GC2. Click on Help, then Contents or press F1PoleVault Systems Installation Installation Stage 2c Check that an image is present, adjust as needed Installation Stage Five, cont’dLoosen all pivot screws and adjust the vertical angle Test the systemFinal installation Adjust the configuration as necessaryRelease the input button Open the sensor and loop a wire around the sensor Optional Accessory Installation PPCInstallation Procedure Priority Page Controller included partsStrip 3/16 of insulation from each conductor on the bare Connect the power supply via the PoleVault switcher Testing and Adjustment Procedure Sensitivity knob adjustmentPriority Page Controller Time DIP switch settings PoleVault Systems Installation Reference Information Reference InformationWall or furniture mountable with included Decora wall plate Lbs 0.1 kgInstallation Reference Information, cont’d Page Extron USA West