Extron electronic PVS 400, 300, 200 manual Installation Stage Five, cont’d, Test the system

Page 40

Installation — Stage Five, cont’d

2.Test the system

a.Ensure power is supplied to the PVS 204SA switcher, and power on the MLC 104 IP Plus.

b.Connect all the input devices (e.g., PC, DVD, document camera, etc.) to the transmitters and power up the input devices. Check that power and signal are present at the transmitters. The LEDs light red when only power is present and light green when power and a signal are present.

c.Power on the projector and with a video source (PC or DVD playing) check that a good image is shown on screen.

Adjust projector settings as follows:

Adjust the rotation (yaw) by turning the unit on the projector pole. Secure the location by tightening the two set screws on the UPB mount plate to the pole

(see below).

Loosen all pivot screws and adjust the vertical angle

(pitch) of the projector. Lock down the four adjustment screws.

Adjust the horizontal tilt (roll) of the projector. Lock down all the remaining adjustment and pivot screws.

Adjust the image settings on the projector (zoom, focus, keystone, brightness, contrast, etc.). Refer to the manufacturer’s user manual.

2a Turn on the MLC 104 IP Plus controller and the PVS 204Sa switcher

2b Connect and turn on the input devices

Vertical

Angle Adjustment

and Pivot

Point Screws

Horizontal Angle

Adjustment and

Pivot Point Screws

Tighten these 2 set screws (one each side) to lock the UPB onto the pole.

Pitch/Vertical Angle

Yaw/RotationRoll/Tilt

Adjuster Plate Locking Screws (4)

2c Check that an image is present, adjust as needed.

2-28 PoleVault Systems Installation • Installation — Stage 5

Image 40
Contents PoleVault Systems Precautions Safety Instructions EnglishConsignes de Sécurité Français Sicherheitsanleitungen DeutschIntroduction PoleVault Systems Installation IntroductionFCC Class a Notice PoleVault System installation and wiring overview Introduction, contdTypical classroom installation PoleVault Systems Installation Introduction PlanningRoom layout RoomExample of a classroom installation Introduction Planning, cont’dLocation of the screen and projector ADA overhead and side clearance requirementsLocation of MediaLink Controller and Wall Plates Example classroom with four speaker installationType and location of the speakers Inventory Introduction Inventory OverviewIncluded items PoleVault System Devices and Hardware, contd PoleVault System Devices and Hardware, cont’dIntroduction Inventory Overview, cont’d PoleVault System Ceiling SpeakersOptional installation hardware Items not includedInstallation tools Outline of installation steps Installation OverviewPoleVault Systems Installation Installation Overview Where it goes Screws up into PCM PoleVault Systems Installation Installation StagePCM 240 Projector Ceiling Mount PMP Projector Mounting Pole2c Install the PMP 2d Screw the adjuster plate onto the PMPMark screen location 1a Mark the screen locationInstallation Stage One, cont’d 2f Slide and lock the projector onto the adjuster plateVerify the image location 2e Attach the bracket to the projectorInstallation Using these dimensions, mark and cut a hole forCut the ceiling tile 5d Screw the PMP into the mounting plate viewed from belowTighten the four T-bar securing screws on the PCM Secure the Projector Ceiling Mount to the ceiling6e Tighten the turnbuckles 6g Attach the safety cable to the PCM Install the ScreenPower outlet installation on PCM This stage involves installing the devices shown below Stage Two Install the Wall Plates and MLC 104 IPMLC 104 IP Plus MediaLink Controller PVS 204SA switcher CablesStage Two Install the Wallplates and MLC 104 IP Plus Install mud rings1d Features for mud ring installation MLC 104 IP Plus mud ringSignal Cable Label color Pull cablesProjector communication cables from 2c Pull the cables at each locationInstallation Stage Two, cont’d Install wall platesTWire stripping lengths Install MediaLink Controller4a Connecting the MLC to the switcher 4c Connect to the LAN using a CAT 5 cable Connect the MLC to the projector withAn RS-232 cable or IR emitter cable, as AppropriateConnections made to the MLC 104 IP Plus 4e Secure the MLC 104 IP Plus to the mud ringStage Three Install the PV SI 3C LP Ceiling Speakers PV SI 3C LP Ceiling SpeakersCut ceiling tile Installation Stage Three, cont’d Cable the speakersPole captive screw connector 4c Wire the captive screw connector Dual mono outputStereo or dual mono output using parallel speaker wiring To terminate the cable, strip the end of the cableFinish speaker installation 5a Apply putty to speaker grillStage Four Install the PMK 450 and the PVS 204SA This stage covers installing the devices shown belowPVS 204SA PoleVault Switcher PMK 450 Pole Mount KitInstallation Stage Four, cont’d Install the PMK 450 Pole Mount kitSwitcher and projector cable overview Pull the cablesInstall the PVS 204SA switcher PMK 450 bottom plate and secure it using velcro3c Wire the captive screw connector for the power supply 3d Set the DIP switches as desiredFinish installing the Pole Mount kit BControl/power cable from the MLC 104 IP PlusConnect the cables to the switcher PVS 204SA cable connections 4d Replace projector on the adjuster plate 4c Attach and screw down rear plateStage Five Configure the System Configure the system1a Load Global Configurator 2 software Launch GC2. Click on Help, then Contents or press F1PoleVault Systems Installation Installation Stage Installation Stage Five, cont’d Loosen all pivot screws and adjust the vertical angle2c Check that an image is present, adjust as needed Test the systemAdjust the configuration as necessary Final installationRelease the input button Optional Accessory Installation PPC Installation ProcedureOpen the sensor and loop a wire around the sensor Priority Page Controller included partsStrip 3/16 of insulation from each conductor on the bare Connect the power supply via the PoleVault switcher Sensitivity knob adjustment Testing and Adjustment ProcedurePriority Page Controller Time DIP switch settings PoleVault Systems Installation Reference Information Reference InformationWall or furniture mountable with included Decora wall plate Lbs 0.1 kgInstallation Reference Information, cont’d Page Extron USA West
Related manuals
Manual 18 pages 30.9 Kb Manual 1 pages 17.57 Kb Manual 29 pages 11.77 Kb Manual 46 pages 60.91 Kb