Enterasys Networks C2H124-48P manual Recommended Procedures to Install New and Existing Stacks

Page 45

Configuring Switches in a Stack

2.Switch IDs are saved against each module. Then, every time a board is power‐cycled, it will initialize with the same switch ID. This is important for port‐specific information (for example: ge.4.12 is the 12th Gigabit Ethernet port on switch # 4).

3.The management election process uses the following precedence to assign a management device:

a.Previously assigned / elected management switch

b.Management assigned priority (values 1‐15)

c.Hardware preference level

d.Highest MAC Address

Recommended Procedures to Install New and Existing Stacks

Important

The following procedures assume that all switches have a clean configuration from manufacturing. When adding a new switch to an already running stack, it is also assumed that the new switch is using the same firmware image version as other switches in the stack.

Installing a New Stackable System of Up to Eight Switches

Use the following procedure to install a new stack of up to eight switches out of the box. Before applying power, make all physical connections with the stack cables as described in “Connecting High‐Speed Stacking Cables” on page 3‐10.

1.Once all of the stack cables have been connected, individually power on each switch from top to bottom (connecting power to a switch is described in “Connecting AC and PoE Power” on page 3‐15).

If the switches are powered on almost simultaneously, the system will automatically select the first one that powers up as the Master switch and the others as Member switches. The switches are assigned unit IDs in the order that they become fully operational.

You can control the unit ID assignment according to the physical position in a stack. When you power up each switch and allow it to become fully operational before applying power to the next switch, the first one becomes the Manager and all the next switches will join that stack (regardless of Priority, Firmware Revision, or MAC Address). The switches are assigned unit IDs in the order that you power on each switch.

Note: Once switch IDs are assigned, they are persistent and will be retained during a power cycle to any or all of the switches.

SecureStack C2 Installation Guide 3-13

Image 45
Contents Enterasys SecureStack C2 Page Page Regulatory Compliance Information Electromagnetic Compatibility EMC Supplement to Product Instructions Vcci Notice Declaration of Conformity Enterasys NETWORKS, INC Firmware License Agreement Viii Page Page Contents Troubleshooting Figures Xiv Who Should Use This Guide About This GuideRelated Documents How to Use This GuideFollowing conventions are used in this guide Conventions Used in This GuidePage Overview IntroductionC2G124-48P Stackable Switch C2G124-48P Stackable Switch C2H124-48P Stackable SwitchHigh-Speed Stack Connections C2H124-48P Stackable SwitchPoE Power over Ethernet Support Redundant Power Supply CapabilityPowered Device Classifications Usage PD Maximum Power Range Connectivity Switch Configuration Using WebViewManagement Description of Mini-GBICsSwitch Configuration Using CLI Commands Lanview Diagnostic LEDsStandards Compatibility Getting HelpGetting Help Network Requirements 10BASE-TX Network 100BASE-TX Network1000BASE-FX Network 1000BASE-T Network 1000BASE-T Network Network Requirements Hardware Installation Unpacking the Switch Considerations Prior to InstallationContents of Switch Carton Quantity Required ToolsPreparing to Install a Mini-GBIC Installing Optional Mini-GBICsMini-GBIC with MT-RJ Connector Mini-GBIC with LC Connector Removing a Mini-GBIC Installing the Switch on a Flat SurfaceChassis Bottom, Rubber Feet Placement Installing the Rubber FeetArea Guidelines for Switch Installation on Flat Surface Guidelines for Flat Surface InstallationRack Mounting the Switch Guidelines for Rackmount InstallationAttaching Brackets and Installing in Rack Attaching the Rackmount Brackets Connecting High-Speed Stacking CablesHigh-Speed Stacking Cable Connections About SecureStack C2 Switch Operation in a Stack Configuring Switches in a StackInstalling a New Stackable System of Up to Eight Switches Recommended Procedures to Install New and Existing StacksImportant Considerations About Using Clear Config in a Stack Switch Rear View Connecting AC and PoE PowerStack Initialization Overview PoE PowerWhat Is Needed Connecting to Console Port for Local ManagementParameter Setting Connecting to an IBM or Compatible Device10 Connecting an IBM PC or Compatible Connecting to a VT Series Terminal11 Connecting a VT Series Terminal Connecting to a ModemConnecting UTP Cables Connecting to the Network13 Connecting a UTP Cable Segment to RJ45 port 14 Four-Wire Crossover Cable RJ45 Pinouts for 10/100BASE-TX TX1+ RX1- TX2+ TX3+ RX3- RX2- TX4+ RX4 Connecting Fiber-Optic Cables to MT-RJ Ports C2G124 Connecting Fiber-Optic Cables to LC Ports Connecting to the Network 19 Cable Connection to LC Fiber-Optic Connectors Initial Logon to Switch Management Completing the InstallationTroubleshooting C2G124-48P Lanview LEDs Using LanviewC2H124-48P Lanview LEDs Color State Recommended Action Lanview LED Diagnostic IndicationsRPS Mgbic Refer to the SecureStack C2 Configuration Guide for the IP Troubleshooting ChecklistReset Button Using the Reset ButtonUsing the Reset Button Using the Reset Button Troubleshooting Table A-1 Switch Specifications ItemSpecification C2G124-48P/C2H124-48P Switch SpecificationsProcessors/Memory Table A-1 Switch Specifications C2H124-48PTable A-2 Mini-GBIC Input/Output Port Specifications Mini-GBIC Input/Output SpecificationsGigabit Ethernet Specifications MGBIC-LC01/MGBIC-MT01 Specifications 1000BASE-SXMGBIC-LC03 Specifications 1000BASE-LX MGBIC-LC09 Specifications 1000BASE-LX MGBIC-02 Specifications 1000BASE-T MGBIC-08 Specifications 1000BASE-ELXTable A-9 MGBIC-08 Optical Specifications Table A-11 MGBIC-02 SpecificationsConsole Port Pinout Assignments Regulatory ComplianceTable A-12 Compliance Standards Regulatory Compliance Regulatory Compliance Specifications Index Index-2