Nortel Networks SRG50 manual Process map for installing and configuring an SRG
Page 26
26Chapter 2 SRG50 overview
Process map for installing and configuring an SRG
Figure 3 Process map for installing and configuring an SRG
The main office is installed and running and the information to support SRG has been configured.
You have reviewed the SRG and BCM50 system requirements and documentation.
Locate the BCM50 that will be converted to the SRG.
Install the physical components, including media bay modules, cabling, telephones, and peripherals, as per the Installation and Maintenance Guide.
Configure the basic parameters of the BCM50 as per the Installation Checklist and Quick Start Guide. (see the Installation and Maintenance Guide (NN40020-302) and the Administration Guide (NN40020-600)).
Complete the initial installation, connect the SRG to the LAN (as required) and WAN (to main office), and test the SRG system, as per the Installation and Maintenance Guide (NN40020-302).
Set up SRG administration, and carry out non-SRG-specific networking and device configuration as per the Administration Guide (NN40020-600), the Networking Configuration Guide (NN40020-603), and the Device Configuration Guide (NN40020-300).