27
Chapter 3
Task summary
The task summary offers a high level, chronological review of the tasks required to configure the SRG50. The paths (Xxxx > Yyyy > Zzzz) direct you to the appropriate Business Element Manager (Element Manager) panels.
Foundation configuration
Foundation configuration refers to configuration that is done as part of BCM50 foundation activities. The items identified here are significant for SRG operation and main office planning and installation.
1Configure the SRG IP address, net mask, and gateway.
Configuration >System > IP Subsystem
External Reference: Installation and Maintenance Guide
2Confirm the number of IP sets and VoIP trunks.
Configuration > Resources > Application Resources
The Licence column indicates the number of resources available. External Reference: Keycode Installation Guide
3Verify the global telephony settings.
Configuration > Telephony > Global Settings
External Reference: Device Configuration Guide
4Configure the Start DN (determined by the dialing plan).
Administration > Utilities > Reset > Cold Reset Telephony Services button > Cold Reset Telephony dialog box > Start DN field
Internal Reference: Basic parameters on page 67
External Reference: Installation and Maintenance Guide
5Verify the DN length.
i) For local calls between telephones on the SRG.
Configuration > Telephony > Dialing Plan > General > Dialing Plan - General panel > Global Settings subpanel > DN length (intercom) field
ii) For incoming calls from the PSTN
Configuration > Telephony > Dialing Plan > Public Network > Dialing Plan - Public Network panel> Public Network Settings subpanel > Public Received number length field