APC Power Supply manual Installation/Maintenance, Input Voltage Circuit Breaker Size

Page 10

Warnings

Installation/Maintenance

Only a certified electrician can do following:

Connect the PDU to its power source

Install a customer-specified, hard-wired power cable

Only a certified electrician or an APC Field Service Engineer can perform maintenance of the PDU.

When connecting the PDU to utility, a circuit breaker must be installed to protect the PDU against short-circuit current. Determine the type of circuit breaker that you need to install:

Input Voltage

Circuit Breaker Size

200V200A

415V100A

Maintenance performed while the PDU is receiving input power

APC does not recommend that you perform maintenance of the PDU while it is receiving input power. However, due to the critical nature of data center loads, this may occur. If you must perform maintenance while the PDU is receiving input power, observe the following precautions to reduce the risk of electric shock:

1.Never work alone.

2.Perform the maintenance only if you are a certified electrician who is trained in the hazards of live electrical installation.

3.Know the procedure for disconnecting electricity to the PDU and the data center in case of an emergency.

4.Wear appropriate personal protective equipment.

5.Use double-insulated tools.

6.Always follow local and site regulations when working on the PDU.

Total power off procedure

1.Set the PDU Main Input to Off.

2.Set the upstream power source circuit breaker to Off.

Register equipment with the fire department

Follow local code ordinances and register all fire code-compliant equipment with the fire department.

2

InfraStruXure Site Planning, Installation, Start-Up

Image 10
Contents InfraStruXure Installation and Start-Up This manual is available in English on the enclosed CD About this Manual Page Contents Start-Up Procedure Configuration Page Cross-reference symbols used in this manual SafetySafety symbols used in this manual OverviewInput Voltage Circuit Breaker Size Installation/MaintenanceTotal power off procedure Register equipment with the fire departmentInfraStruXure PDU DimensionsSite Preparation NetShelter VX Seismic EnclosureNetShelter VX Enclosure Space Considerations Weight Considerations Component Maximum Unpacked Maximum PackagedHeat Output InfraStruXure PDU Heat OutputElectrical requirements Electrical Requirements and SpecificationsProcedures requiring a licensed electrician 200V Input 415V InputBasic Installation Procedure Licensed electrician must connect the power source Join adjacent enclosures Installation ProceduresJoin Adjacent Enclosures and Bolt Enclosures to the Floor Bolt Enclosures to the FloorEnsure Total Power Off Access the PDU Main Input switch Connect the Power Source to the PDUAttach conduit to the PDU for the input conductors Installation Procedures Connect the Power Source to the PDU Torque specifications and tools required Install a circuit breakerRoute the input conductors to the main input circuit switch Terminal Torque ToolsConnect input conductors Output relay specifications OverviewHow to connect contacts to the PDU Monitoring Unit InfraStruXure Site Planning, Installation, Start-Up Cable Ladders for overhead wiring across rows Install the Rack Power Distribution Units PDU Install InfraStruXure Rack-Mount DevicesInstall the Rack Automatic Transfer Switches ATS Install the InfraStruXure Manager and Hub or SwitchRoute and Attach Overhead Wiring Route and attach power cables to equipment racksInstallation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Wiring Under the Floor Alternative Installation Procedures Wiring Under the Floor Alternative Route Data Cables to the InfraStruXure Manager Hub or Switch Connect network cables to InfraStruXure componentsOverhead routing Safety warnings Start-Up ProcedureEnsure that all power is off Apply power to the system Start-Up Procedure InfraStruXure System Page Configuration Configure the InfraStruXure ManagerPage How to Apply Power to the System Appendix A-System OperationHow to Ensure Total Power Off Page APC Worldwide Customer Support