Start-Up Procedure
Safety warnings
Only APC Field Service Engineers or qualified,
Before you proceed, ensure that power is off by following the procedure in this section.
Ensure that all power is off
1. Open (turn OFF) the PDU main input.
2. Set the upstream input circuit breaker (utility or UPS) to the OFF or Locked Out position.
InfraStruXure Site Planning, Installation, | 29 |