APC Power Supply manual Start-Up Procedure

Page 6

Ensure Total Power Off . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

Connect the Power Source to the PDU . . . . . . . . . . . . . . . . . . . 13

Access the PDU Main Input switch . . . . . . . . . . . . . . . . . . . 13

Attach conduit to the PDU for the input conductors . . . . . . . 13

Install a circuit breaker . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Route the input conductors to the main input circuit switch . 15

Torque specifications and tools required . . . . . . . . . . . . . . . 15

Connect input conductors . . . . . . . . . . . . . . . . . . . . . . . . 16

Connect User Contact Inputs and Output Relays to

the User Connection Plate . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

How to connect contacts to the PDU Monitoring Unit . . . . . . 18

Install Shielding Troughs, Shielding Partitions,

and Cable Ladders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

Shielding Troughs and Shielding Partitions for overhead

wiring along rows . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19 Cable Ladders for overhead wiring across rows . . . . . . . . . . 20

Install InfraStruXure Rack-Mount Devices . . . . . . . . . . . . . . . . . 21

Install the Rack Automatic Transfer Switches (ATS) . . . . . . . . 21

Install the Rack Power Distribution Units (PDU) . . . . . . . . . . 21

Install the InfraStruXure Manager and Hub (or Switch) . . . . . 21

Install the APC Environmental Monitoring Unit . . . . . . . . . . 21

Route and Attach Overhead Wiring . . . . . . . . . . . . . . . . . . . . . 22

Route and attach power cables to equipment racks . . . . . . . 22

Wiring Under the Floor (Alternative) . . . . . . . . . . . . . . . . . . . . 25

Route Data Cables to the InfraStruXure

Manager Hub (or Switch) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27

Connect network cables to InfraStruXure components

. . . . . 27

Route network cables to the InfraStruXure

 

Manager hub (or switch)

. . . . . 28

Start-Up Procedure

29

Safety warnings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29

Ensure that all power is off . . . . . . . . . . . . . . . . . . . . . . . . 29

Apply power to the system . . . . . . . . . . . . . . . . . . . . . . . . 30

iv

InfraStruXure Site Planning, Installation, Start-Up

Image 6
Contents InfraStruXure Installation and Start-Up This manual is available in English on the enclosed CD About this Manual Page Contents Start-Up Procedure Configuration Page Cross-reference symbols used in this manual SafetySafety symbols used in this manual OverviewInput Voltage Circuit Breaker Size Installation/MaintenanceTotal power off procedure Register equipment with the fire departmentInfraStruXure PDU DimensionsSite Preparation NetShelter VX Seismic EnclosureNetShelter VX Enclosure Space Considerations Weight Considerations Component Maximum Unpacked Maximum PackagedHeat Output InfraStruXure PDU Heat OutputElectrical requirements Electrical Requirements and SpecificationsProcedures requiring a licensed electrician 200V Input 415V InputBasic Installation Procedure Licensed electrician must connect the power source Join adjacent enclosures Installation ProceduresJoin Adjacent Enclosures and Bolt Enclosures to the Floor Bolt Enclosures to the FloorEnsure Total Power Off Connect the Power Source to the PDU Access the PDU Main Input switchAttach conduit to the PDU for the input conductors Installation Procedures Connect the Power Source to the PDU Torque specifications and tools required Install a circuit breakerRoute the input conductors to the main input circuit switch Terminal Torque ToolsConnect input conductors Output relay specifications OverviewHow to connect contacts to the PDU Monitoring Unit InfraStruXure Site Planning, Installation, Start-Up Cable Ladders for overhead wiring across rows Install the Rack Power Distribution Units PDU Install InfraStruXure Rack-Mount DevicesInstall the Rack Automatic Transfer Switches ATS Install the InfraStruXure Manager and Hub or SwitchRoute and Attach Overhead Wiring Route and attach power cables to equipment racksInstallation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Wiring Under the Floor Alternative Installation Procedures Wiring Under the Floor Alternative Route Data Cables to the InfraStruXure Manager Hub or Switch Connect network cables to InfraStruXure componentsOverhead routing Start-Up Procedure Safety warningsEnsure that all power is off Apply power to the system Start-Up Procedure InfraStruXure System Page Configuration Configure the InfraStruXure ManagerPage How to Apply Power to the System Appendix A-System OperationHow to Ensure Total Power Off Page APC Worldwide Customer Support