Start-Up Procedure: InfraStruXure System

Apply power to the system

1.Set the upstream input circuit breaker (utility or UPS) to ON.

2.Ensure R-S-T clockwise phase rotation at the top of the main input switch on the PDU, using a phase rotation meter.

3.Close (turn ON) the main input switch on the PDU.

4.Verify R-S-T clockwise phase rotation at the top of the primary winding of the transformer, using a phase rotation meter.

5.Verify that the proper voltage is present on the secondary winding of the transformer (200 or 173V, metered phase-to-phase), using a true RMS voltmeter.

30

InfraStruXure Site Planning, Installation, Start-Up

Image 38
Contents InfraStruXure Installation and Start-Up This manual is available in English on the enclosed CD About this Manual Page Contents Start-Up Procedure Configuration Page Cross-reference symbols used in this manual SafetySafety symbols used in this manual OverviewInput Voltage Circuit Breaker Size Installation/MaintenanceTotal power off procedure Register equipment with the fire departmentInfraStruXure PDU DimensionsSite Preparation NetShelter VX Seismic EnclosureNetShelter VX Enclosure Space Considerations Weight Considerations Component Maximum Unpacked Maximum PackagedHeat Output InfraStruXure PDU Heat OutputElectrical requirements Electrical Requirements and SpecificationsProcedures requiring a licensed electrician 200V Input 415V InputBasic Installation Procedure Licensed electrician must connect the power source Join adjacent enclosures Installation ProceduresJoin Adjacent Enclosures and Bolt Enclosures to the Floor Bolt Enclosures to the FloorEnsure Total Power Off Attach conduit to the PDU for the input conductors Connect the Power Source to the PDUAccess the PDU Main Input switch Installation Procedures Connect the Power Source to the PDU Torque specifications and tools required Install a circuit breakerRoute the input conductors to the main input circuit switch Terminal Torque ToolsConnect input conductors Output relay specifications OverviewHow to connect contacts to the PDU Monitoring Unit InfraStruXure Site Planning, Installation, Start-Up Cable Ladders for overhead wiring across rows Install the Rack Power Distribution Units PDU Install InfraStruXure Rack-Mount DevicesInstall the Rack Automatic Transfer Switches ATS Install the InfraStruXure Manager and Hub or SwitchRoute and Attach Overhead Wiring Route and attach power cables to equipment racksInstallation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Wiring Under the Floor Alternative Installation Procedures Wiring Under the Floor Alternative Route Data Cables to the InfraStruXure Manager Hub or Switch Connect network cables to InfraStruXure componentsOverhead routing Ensure that all power is off Start-Up ProcedureSafety warnings Apply power to the system Start-Up Procedure InfraStruXure System Page Configuration Configure the InfraStruXure ManagerPage How to Apply Power to the System Appendix A-System OperationHow to Ensure Total Power Off Page APC Worldwide Customer Support