APC Power Supply Installation Procedures, Join adjacent enclosures, Bolt Enclosures to the Floor

Page 19

Installation Procedures

Join Adjacent Enclosures and Bolt Enclosures to the Floor

Join adjacent enclosures

To join NetShelter VX Enclosures, see the installation manual included with your enclosures.

See also

Bolt Enclosures to the Floor

Proper anchoring hardware must be in place before starting this procedure.

To bolt the PDU and enclosures to the floor, follow these steps for each enclosure: 1. Remove the front and rear skirts on the enclosure.

2.Insert two bolts through each plate and the holes in the plinth, using the bolt plate (included). Screw the bolts into the pre-installed anchoring hardware in the floor.

3. Tighten the bolts to 81 n·m, using a torque wrench.

InfraStruXure Site Planning, Installation, Start-Up

11

Image 19
Contents InfraStruXure Installation and Start-Up This manual is available in English on the enclosed CD About this Manual Page Contents Start-Up Procedure Configuration Page Overview SafetySafety symbols used in this manual Cross-reference symbols used in this manualRegister equipment with the fire department Installation/MaintenanceTotal power off procedure Input Voltage Circuit Breaker SizeNetShelter VX Seismic Enclosure DimensionsSite Preparation InfraStruXure PDUNetShelter VX Enclosure Space Considerations Component Maximum Unpacked Maximum Packaged Weight ConsiderationsInfraStruXure PDU Heat Output Heat Output200V Input 415V Input Electrical Requirements and SpecificationsProcedures requiring a licensed electrician Electrical requirementsBasic Installation Procedure Licensed electrician must connect the power source Bolt Enclosures to the Floor Installation ProceduresJoin Adjacent Enclosures and Bolt Enclosures to the Floor Join adjacent enclosuresEnsure Total Power Off Access the PDU Main Input switch Connect the Power Source to the PDUAttach conduit to the PDU for the input conductors Installation Procedures Connect the Power Source to the PDU Terminal Torque Tools Install a circuit breakerRoute the input conductors to the main input circuit switch Torque specifications and tools requiredConnect input conductors Overview Output relay specificationsHow to connect contacts to the PDU Monitoring Unit InfraStruXure Site Planning, Installation, Start-Up Cable Ladders for overhead wiring across rows Install the InfraStruXure Manager and Hub or Switch Install InfraStruXure Rack-Mount DevicesInstall the Rack Automatic Transfer Switches ATS Install the Rack Power Distribution Units PDURoute and attach power cables to equipment racks Route and Attach Overhead WiringInstallation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Wiring Under the Floor Alternative Installation Procedures Wiring Under the Floor Alternative Connect network cables to InfraStruXure components Route Data Cables to the InfraStruXure Manager Hub or SwitchOverhead routing Safety warnings Start-Up ProcedureEnsure that all power is off Apply power to the system Start-Up Procedure InfraStruXure System Page Configure the InfraStruXure Manager ConfigurationPage Appendix A-System Operation How to Apply Power to the SystemHow to Ensure Total Power Off Page APC Worldwide Customer Support