Start-Up Procedure: InfraStruXure System
6. Close (turn ON) the Main Output circuit breaker on the PDU.
When the Main Output circuit breaker is closed, the power distribution circuit breaker panels are energized.
7. Close (turn ON) the PDU distribution panel circuit breakers.
When the distribution panel circuit breakers are closed, the PDU power cables and connected equipment are energized.
InfraStruXure Site Planning, Installation, | 31 |