Installation Procedures: Wiring Under the Floor (Alternative)
4. At the circuit breaker panel, cut the wires to the proper length, and connect the power cable’s individual wires:
a. If you have branch
current monitoring installed, route each
phase conductor through a current sensor. If it is a
the L1, L2, and L3 wires through separate current sensors.
b. Connect the L1, L2, and
L3 wires to the circuit breaker(s). The illustration at right shows a
c. Connect the neutral wire to the closest open termination point on the Neutral Bar.
d. Connect the PE wire to the closest open termination point on the PE Bar.
5.Connect the neutral wire to the neutral bar and the PE wire to the isolated ground bar.
26 | InfraStruXure Site Planning, Installation, |