APC Power Supply manual Basic Installation Procedure

Page 17

Basic Installation Procedure

This section provides the basic steps that you need to perform when installing InfraStruXure power and rack components. Follow the references provided with each step for detailed instructions.

Do not begin installing your InfraStruXure system without an APC Field Service Engineer present.

1.Unpack the components according to the unpacking instructions included on the outside of the packaging or in the installation manual included with the component.

Make sure that all boxes and packaging are empty before discarding them.

2.Determine the correct placement of your system components by studying your APC InfraStruXure configure-to-order (CTO) report. Move the InfraStruXure PDU and enclosures to their final location.

If installing InfraStruXure on a raised floor, make sure that the raised- floor structure has a kg/m2 rating that will support the full weight of the InfraStruXure installation. See “Weight Considerations” on page 6.

3. Join adjacent NetShelter enclosures.

For instructions on joining adjacent NetShelter VX Seismic Enclosures, see the installation manual included with your enclosures.

See also

4. Bolt enclosures to the floor.

See page 11 for detailed instructions.

5. Ensure total power off.

See page 12 for detailed instructions.

InfraStruXure Site Planning, Installation, Start-Up

9

Image 17
Contents InfraStruXure Installation and Start-Up This manual is available in English on the enclosed CD About this Manual Page Contents Start-Up Procedure Configuration Page Safety symbols used in this manual SafetyCross-reference symbols used in this manual OverviewTotal power off procedure Installation/MaintenanceInput Voltage Circuit Breaker Size Register equipment with the fire departmentSite Preparation DimensionsInfraStruXure PDU NetShelter VX Seismic EnclosureNetShelter VX Enclosure Space Considerations Component Maximum Unpacked Maximum Packaged Weight ConsiderationsInfraStruXure PDU Heat Output Heat OutputProcedures requiring a licensed electrician Electrical Requirements and SpecificationsElectrical requirements 200V Input 415V InputBasic Installation Procedure Licensed electrician must connect the power source Join Adjacent Enclosures and Bolt Enclosures to the Floor Installation ProceduresJoin adjacent enclosures Bolt Enclosures to the FloorEnsure Total Power Off Attach conduit to the PDU for the input conductors Connect the Power Source to the PDUAccess the PDU Main Input switch Installation Procedures Connect the Power Source to the PDU Route the input conductors to the main input circuit switch Install a circuit breakerTorque specifications and tools required Terminal Torque ToolsConnect input conductors Overview Output relay specificationsHow to connect contacts to the PDU Monitoring Unit InfraStruXure Site Planning, Installation, Start-Up Cable Ladders for overhead wiring across rows Install the Rack Automatic Transfer Switches ATS Install InfraStruXure Rack-Mount DevicesInstall the Rack Power Distribution Units PDU Install the InfraStruXure Manager and Hub or SwitchRoute and attach power cables to equipment racks Route and Attach Overhead WiringInstallation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Wiring Under the Floor Alternative Installation Procedures Wiring Under the Floor Alternative Connect network cables to InfraStruXure components Route Data Cables to the InfraStruXure Manager Hub or SwitchOverhead routing Ensure that all power is off Start-Up ProcedureSafety warnings Apply power to the system Start-Up Procedure InfraStruXure System Page Configure the InfraStruXure Manager ConfigurationPage Appendix A-System Operation How to Apply Power to the SystemHow to Ensure Total Power Off Page APC Worldwide Customer Support