Site Preparation – Installation Space Requirements
Clearance for stand-alone 13.85 in/352 mm Enclosures
(B)
UPS
(C)
(E)
(A)
Conduit Box (F)
(D)
Stabilizing Bracket, left and right
(G)
Space requirements | in | mm |
|
|
|
Minimum clearance above UPS (A) | 20.00 | 508 |
|
|
|
UPS depth (B) | 32.99 | 854 |
|
|
|
UPS width | 13.85 | 352 |
|
|
|
Minimum rear service clearance* (compliant with NEC 110.26 | 36.00 | 914 |
for North America) (D) |
|
|
|
|
|
Minimum front clearance (E) | 40.00 | 1,000 |
|
|
|
Conduit Box, depth (F) | 3.46 | 88 |
|
|
|
No side clearance required (add width of Stabilizing Bracket for | 0 | 0 |
floor anchoring if applicable) |
|
|
|
|
|
Stabilizing Bracket width | 3.34 | 85 |
|
|
|
Total installation depth, inclusive of Front Panel, Conduit Box | 112.45 | 2.840 |
and minimum front and rear clearances (G) |
|
|
|
|
|
*) Minimum free rear space for ventilation 4 in/100 mm.
For the stability of 13.85 in/352 mm