American Power Conversion 208/220 Site Preparation Checklist, System components. Have you

Page 23

Site Preparation Checklist

System components. Have you –

determined minimum battery run time requirement based on load (kW and kVA) and selected the proper number of APC XR Enclosures (SUVTBXR2B6S, SUVTXR2B6S and SUVTBXR6B6S, SUVTXR6B6S) and Battery Unit (SYBT1). Always install a whole Battery Module (4 Battery Units) at a time.

considered Service Program or Extended Warranty plan?

Site Preparation. Have you –

verified that input voltage and current are available?

considered correct operating space, floor strength (see Installation Space Requirements), cooling, and environment (see Operating Environment).

reviewed all electrical work to determine wiring requirements?

Arrival Preparation. Have you –

verified that space and handling equipment are available to receive the UPS/XR Enclosure? (Including unloading the UPS/XR Enclosure from the delivery truck).

scheduled an authorized electrician to install the UPS/XR Enclosure?

990-1598B Smart-UPS® VT 10-30 kVA, 208/220 V Site Preparation and Installation Manual

17

Image 23
Contents Smart-UPSVT Page Smart-UPSVT 10-30 kVA 208/220 Page Contents Mechanical assembly Environmental symbols General Safety InstructionsSymbols used in this guide General safety Introduction 20.59 in/523 mm Enclosures UPS Family Range and Components13.85 in/352 mm Enclosures Type label Serial number  User interface Upper Cover Plate rear  Upper part of Conduit Box Connection Interface rearFoot print Humidity Sensor Clearance for 20.59 in/523 mm Enclosures Installation Space RequirementsClearance for stand-alone 13.85 in/352 mm Enclosures Audible noise Operating EnvironmentOperating conditions Heat dissipationRecommended current protection Minimum breaker settings for 10 kVA UPSMinimum setting of breakers for 30 kVA UPS Minimum breaker settings for 15 kVA UPSMinimum breaker settings for 20 kVA UPS Diameter EPO switch wiringEPO Basic Wiring OverviewSystem components. Have you Site Preparation Checklist  Stabilizing BracketsLeveling Feet Setting the leveling feetHole positions for floor anchors stand-alone Enclosures Floor AnchoringDrilling floor holes for floor anchoring Floor anchoring of stand-alone systems System-Electrical Information Electrical InstallationUPS ratings 220 Source connections Utility source Provided by others Utility source Wiring Wiring procedure single mains Input/Output Wiring Single Mains defaultMains  input  Neutralcables   Output  cables Wiring procedure dual mains Input/Output Wiring Dual MainsElectrical Installation Input/Output Wiring Dual Mains Wiring to battery bank or battery racks Bat+ External Battery WiringCommunication Wiring to EPO and Optional Equipment Pin connections J106 UPS to J200 XR Enclosure option Pin connections J106 XR Enclosure and J108 EPOJ106 Charging control switch Switch J200 XR Batteries +24V Normally Closed Pin connections J108 for EPO wiring optionsFront panel removal Connection of APC Humidity Sensor  Electrical Installation Connection of APC Humidity Sensor Wiring Verification Procedure Installation Site Checklist 990-1598B