American Power Conversion 208/220 Operating Environment, Operating conditions, Heat dissipation

Page 18

Operating Environment

Operating conditions

Install the UPS in an indoor, temperature-controlled area, free of conductive contaminants.

Note

Temperature

Range:

32° to 104°F /

0° to 40°C

Keep Ventilated

Front-to-Rear Airflow (see space considerations)

Relative

Humidity: <95%

Non-condensing

No Conductive

Dust or

Corrosive

Fumes

Altitude derating table:

3,000 ft/914 m: 100% load

4,500 ft/1371 m: 95% load

6,000 ft/1828 m: 91% load

8,000 ft/2438 m: 86% load

10,000 ft/3048 m: 82% load

Heat dissipation

 

BTU/hr at fully

 

BTU/hr at fully

UPS size

charged batteries

UPS size

charged batteries

 

 

 

 

10 kVA

1,774

20 kVA

3,624

 

 

 

 

15 kVA

2,866

30 kVA

5,486

 

 

 

 

Audible noise

UPS Sizes

Audible noise at 100% load

Audible noise at <70% load

(1.09 yard/1 m from the UPS)

(1.09 yard/1 m from the UPS)

 

 

 

10-15 kVA

54 dBA

45.4 dBA

 

 

 

20-30 kVA

58 dBA

48.5 dBA

 

 

 

12

Smart-UPS® VT 10-30 kVA, 208/220 V Site Preparation and Installation Manual 990-1598B

Image 18
Contents Smart-UPSVT Page Smart-UPSVT 10-30 kVA 208/220 Page Contents Mechanical assembly General Safety Instructions Symbols used in this guideEnvironmental symbols General safety Introduction UPS Family Range and Components 13.85 in/352 mm Enclosures20.59 in/523 mm Enclosures Serial number Type labelUser interface  Connection Interface rear  Upper Cover Plate rear  Upper part of Conduit BoxFoot print Humidity Sensor Installation Space Requirements Clearance for 20.59 in/523 mm EnclosuresClearance for stand-alone 13.85 in/352 mm Enclosures Heat dissipation Operating EnvironmentOperating conditions Audible noiseMinimum breaker settings for 10 kVA UPS Recommended current protectionMinimum breaker settings for 15 kVA UPS Minimum breaker settings for 20 kVA UPSMinimum setting of breakers for 30 kVA UPS EPO switch wiring DiameterBasic Wiring Overview EPOSite Preparation Checklist System components. Have youStabilizing Brackets  Setting the leveling feet Leveling FeetFloor Anchoring Drilling floor holes for floor anchoringHole positions for floor anchors stand-alone Enclosures Floor anchoring of stand-alone systems Electrical Installation System-Electrical InformationUPS ratings 220 Source connections Utility source Provided by others Utility source Wiring Input/Output Wiring Single Mains default Wiring procedure single mainsMains  input  Neutralcables   Output  cables Input/Output Wiring Dual Mains Wiring procedure dual mainsElectrical Installation Input/Output Wiring Dual Mains External Battery Wiring Wiring to battery bank or battery racks Bat+Communication Wiring to EPO and Optional Equipment Pin connections J106 XR Enclosure and J108 EPO Pin connections J106 UPS to J200 XR Enclosure optionJ106 Charging control switch Switch J200 XR Batteries Pin connections J108 for EPO wiring options +24V Normally ClosedConnection of APC Humidity Sensor Front panel removal  Electrical Installation Connection of APC Humidity Sensor Wiring Verification Procedure Installation Site Checklist 990-1598B