American Power Conversion 208/220 installation manual Installation Site Checklist

Page 47

Installation Site Checklist

This checklist should be completed by the electrician after the wiring has been completed:

Installed at (company name, date, contact)__________________________________________

Name and telephone number of electrician: ___________________________________________

UPS serial number: ______________________________________________________________

Input Circuit Breaker size and type: _________________________________________________

Output fuse size and type: ________________________________________________________

Location of protection devices (room):______________________________________________

Breaker ID: ___________________________________________________________________

EPO type: ____________________________________________________________________

Wire size and type: _____________________________________________________________

Ground connection method and location: ________________________________________

990-1598B Smart-UPS® VT 10-30 kVA, 208/220 V Site Preparation and Installation Manual

41

Image 47
Contents Smart-UPSVT Page Smart-UPSVT 10-30 kVA 208/220 Page Contents Mechanical assembly Environmental symbols General Safety InstructionsSymbols used in this guide General safety Introduction 20.59 in/523 mm Enclosures UPS Family Range and Components13.85 in/352 mm Enclosures Type label Serial number  User interface Upper Cover Plate rear  Upper part of Conduit Box Connection Interface rearFoot print Humidity Sensor Clearance for 20.59 in/523 mm Enclosures Installation Space RequirementsClearance for stand-alone 13.85 in/352 mm Enclosures Audible noise Operating EnvironmentOperating conditions Heat dissipationRecommended current protection Minimum breaker settings for 10 kVA UPSMinimum setting of breakers for 30 kVA UPS Minimum breaker settings for 15 kVA UPSMinimum breaker settings for 20 kVA UPS Diameter EPO switch wiringEPO Basic Wiring OverviewSystem components. Have you Site Preparation Checklist  Stabilizing BracketsLeveling Feet Setting the leveling feetHole positions for floor anchors stand-alone Enclosures Floor AnchoringDrilling floor holes for floor anchoring Floor anchoring of stand-alone systems System-Electrical Information Electrical InstallationUPS ratings 220 Source connections Utility source Provided by others Utility source Wiring Wiring procedure single mains Input/Output Wiring Single Mains defaultMains  input  Neutralcables   Output  cables Wiring procedure dual mains Input/Output Wiring Dual MainsElectrical Installation Input/Output Wiring Dual Mains Wiring to battery bank or battery racks Bat+ External Battery WiringCommunication Wiring to EPO and Optional Equipment Pin connections J106 UPS to J200 XR Enclosure option Pin connections J106 XR Enclosure and J108 EPOJ106 Charging control switch Switch J200 XR Batteries +24V Normally Closed Pin connections J108 for EPO wiring optionsFront panel removal Connection of APC Humidity Sensor  Electrical Installation Connection of APC Humidity Sensor Wiring Verification Procedure Installation Site Checklist 990-1598B