American Power Conversion 208/220 J106 Charging control switch Switch J200 XR Batteries

Page 41

Electrical Installation – Communication Wiring to EPO and Optional

When connecting the Q3 auxiliary signal, use gold-plated N/C auxiliary switch on Q3.

Note

XR Enclosure, APC Maintenance Bypass Panel, and Generator Control wiring

J106

 

 

 

 

 

 

 

8

 

 

 

 

 

 

 

 

 

 

Charging control switch

 

 

 

 

 

 

 

7

 

 

 

 

 

 

 

 

 

 

 

 

6

 

 

 

 

 

 

 

 

 

Q3

 

 

 

 

 

 

 

 

 

5

 

 

 

switch

 

 

 

 

 

 

 

 

 

4

 

 

 

 

 

 

 

4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3

 

3

 

 

 

 

 

2

 

2

 

 

 

 

 

 

 

 

 

 

1

 

1

 

 

 

 

 

 

 

 

 

 

 

 

 

J200 (XR Batteries)

Pins 1 through 4 are for battery measurement (only applicable to APC XR Enclosures). Pins 5 through 6 are for external maintenance bypass Q3.

Pins 7 and 8 are for external charge control.

990-1598B Smart-UPS® VT 10-30 kVA, 208/220 V Site Preparation and Installation Manual

35

Image 41
Contents Smart-UPSVT Page Smart-UPSVT 10-30 kVA 208/220 Page Contents Mechanical assembly Environmental symbols General Safety InstructionsSymbols used in this guide General safety Introduction 20.59 in/523 mm Enclosures UPS Family Range and Components13.85 in/352 mm Enclosures Type label Serial number  User interface Upper Cover Plate rear  Upper part of Conduit Box Connection Interface rearFoot print Humidity Sensor Clearance for 20.59 in/523 mm Enclosures Installation Space RequirementsClearance for stand-alone 13.85 in/352 mm Enclosures Operating conditions Operating EnvironmentHeat dissipation Audible noiseRecommended current protection Minimum breaker settings for 10 kVA UPSMinimum setting of breakers for 30 kVA UPS Minimum breaker settings for 15 kVA UPSMinimum breaker settings for 20 kVA UPS Diameter EPO switch wiringEPO Basic Wiring OverviewSystem components. Have you Site Preparation Checklist  Stabilizing BracketsLeveling Feet Setting the leveling feetHole positions for floor anchors stand-alone Enclosures Floor AnchoringDrilling floor holes for floor anchoring Floor anchoring of stand-alone systems System-Electrical Information Electrical InstallationUPS ratings 220 Source connections Utility source Provided by others Utility source Wiring Wiring procedure single mains Input/Output Wiring Single Mains defaultMains  input  Neutralcables   Output  cables Wiring procedure dual mains Input/Output Wiring Dual MainsElectrical Installation Input/Output Wiring Dual Mains Wiring to battery bank or battery racks Bat+ External Battery WiringCommunication Wiring to EPO and Optional Equipment Pin connections J106 UPS to J200 XR Enclosure option Pin connections J106 XR Enclosure and J108 EPOJ106 Charging control switch Switch J200 XR Batteries +24V Normally Closed Pin connections J108 for EPO wiring optionsFront panel removal Connection of APC Humidity Sensor  Electrical Installation Connection of APC Humidity Sensor Wiring Verification Procedure Installation Site Checklist 990-1598B