IBM SA41-5155-05 Overview of RISC-to-RISC Upgrades and Data Migrations, What is in this Road Map?

Page 13

Chapter 1. Overview of RISC-to-RISC Upgrades and Data Migrations

The road map lists important considerations and activities that are critical to the successful model upgrade of a system. Although this road map is not designed to be an all inclusive how-to source for activities relating to upgrading your system, it covers the essentials by guiding you to the proper source. Follow all the steps in the order presented and notify your IBM® representative for assistance if you run into difficulties.

This road map also covers how to perform a model to model data migration. A data migration can be performed from almost any iSeries 400 model to any model. The source model must be at the same release as the new model to correctly complete the data migration. Data migration involves a new system with a new serial number.

For an overview of the RISC-to-RISC upgrades and data migration, refer to “Upgrade process flow” on page 2 and the “Data migration process flow” on page 4.

What is in this Road Map?

This road map covers the following RISC-to-RISC upgrades:

Note: The current system may require hardware upgrades or configuration changes to satisfy capacity and compatibility requirements of new software and hardware.

vIBM AS/400 Model 170 to IBM AS/400 Model 170

There are no upgrades into or out of a Model 170. The Data Migration section of this book covers the procedure used to perform a data move from the source system to the new iSeries model.

vIBM ~iSeries Model 270 to IBM ~iSeries Model 270

There are no upgrades into or out of a Model 270. The Data Migration section of this book covers the procedure used to perform a data move from the source system to the new iSeries model.

vIBM AS/400 Models 5xx to IBM AS/400 Models 7xx

vIBM AS/400 Models 6xx to IBM AS/400 Models 7xx

vIBM AS/400 Models 7xx to IBM AS/400 Models 7xx

vIBM AS/400 Models Sxx or IBM AS/400 Models 5xx to IBM ~iSeries

Models 8xx

There are no model upgrades into a Model 8xx from a Model 5xx, 6xx, Sxx, or SBx. However, some hardware may be moved from the 5xx into a migration I expansion unit (I/O and disk unit). The Data Migration section of this book covers the procedure used to perform a data move from the source system to the new iSeries 400 model.

vIBM AS/400 Models 6xx to IBM ~iSeries Models 8xx

vIBM AS/400 Models 7xx to IBM ~iSeries Models 8xx

vIBM ~iSeries Models 8xx to IBM ~iSeries Models 8xx

© Copyright IBM Corp. 1997, 2001

1

Image 13
Contents ISeries 940x RISC-to-RISC Road Map Page ISeries 940x RISC-to-RISC Road Map Sixth Edition May Contents Iv iSeries 940x RISC-to-RISC Road Map V5R1 Who Should Read This Book ISeries 940x RISC-to-RISC Road Map, SA41-5155-05Conventions and Terminology Used in This Book V4R4M0 Prerequisite and related information Under the System Planning and Installation topicOperations Navigator How to send your commentsISeries 940x RISC-to-RISC Road Map, SA41-5155-05 ISeries 940x RISC-to-RISC Road Map V5R1 What is in this Road Map? Overview of RISC-to-RISC Upgrades and Data MigrationsUpgrade process flow What is an Upgrade?What is a Data Migration? How Long will the Upgrade Take?Hardware Investment for Upgrading Data migration process flow How Long will the Data Migration Take? Books to Use for Software Release UpgradesISeries 940x RISC-to-RISC Road Map V5R1 Planning Your Order for Upgrading or Data Migration Determining Your Upgrade NeedsHow to Gather Performance Information How to Gather Configuration InformationVersion 4 Software Items Prerequisites Before Placing an OrderOther Software Related Items Hardware ConsiderationsServices and Other Assistance System Configuration ConsiderationsModel-specific Considerations for Placing an Order Upgrading from a 4xx, 5xx, Sxx, or 6xx to a Migrating from a 5xx to an Who is Responsible for Ordering the Upgrade? Placing the Upgrade OrderUpgrading from a 6xx or 7xx to an Sending the Order to a Software Service Provider Other Than How to Get Help with the OrderSending the Order to IBM ISeries 940x RISC-to-RISC Road Map V5R1 Who is Responsible for Upgrading the System Procedure for an Upgrade RISC-to-RISCPreparing the Current System What to Do When the Hardware ArrivesThis is where you load the new operating system Preparing for System Assurance prior to hardware upgrade Print Disk Configuration Status of the installed system ISeries 940x RISC-to-RISC Road Map V5R1 System Assurance Checkpoint Managing your new system I/O resources Installing the Hardware for the RISC-to-RISC UpgradeInformation Center under System planning and installation ISeries 940x RISC-to-RISC Road Map V5R1 Change Description Label display appears Perform a normal IPL Performing a new system backupProcedure for an Upgrade RISC-to-RISC Systems Management Work management- Work Management Manuals Prerequisites for data migration Risc to Risc Procedure for a Data Migration RISC-to-RISCPreparing the source system for the migration Data migration RISC-to-RISC Procedure for a Data Migration RISC-to-RISC ISeries 940x RISC-to-RISC Road Map V5R1 ISeries and AS/400 Data Migration Services Appendix A. AS/400 Global ServicesLpar Planning and Implementation Services ISeries Planning and Migration ServicesAS/400 Solution Services Installation Services Related Support ServicesConsulting Services Performance ExaminationsMidrange Enhanced Software Service Mress ISeries 940x RISC-to-RISC Road Map V5R1 IBM Http Server for AS/400 Appendix B. Considerations and SolutionsOperations Console OptiConnect SRC A900 2000 RecoveryIntegrated Netfinity Server Clustering and Logical PartitionsHow to Move Freed Database Files without New Members Command to restore the file. For a logical file, use PTF ISeries 940x RISC-to-RISC Road Map V5R1 Appendix D. Notices IBM TrademarksAppendix D. Notices ISeries 940x RISC-to-RISC Road Map V5R1 Rtvcfgsrc IndexISeries 940x RISC-to-RISC Road Map V5R1 How satisfied are you that the information in this book is Readers’ Comments We’d Like to Hear from YouBusiness Reply Mail Page SA41-5155-05