IBM SA41-5155-05 manual Procedure for a Data Migration RISC-to-RISC

Page 43

Chapter 4. Procedure for a Data Migration (RISC-to-RISC)

This chapter guides you through a data migration (RISC to RISC) that moves data from one iSeries model server to another. It requires two servers with unique serial numbers. To migrate data from one iSeries 400 server to an upgraded model that retains the original serial number, refer to “Chapter 3. Procedure for an Upgrade (RISC-to-RISC)” on page 17.

Prerequisites for data migration (RISC to RISC)

This procedure assumes that:

vThe target system is set up and is running, with only SLIC and the base OS installed (FC 0205) and that the DASD has been configured for ASP 1. For help with DASD configuration, you may wish to investigate the IBM billable service DASD management.

vYou have completed a clean-up of the source system, and obtained current performance benchmarks.

Note: Failure to obtain performance benchmarks may make it extremely difficult to provide support for your iSeries system after moving to the new model. IBM strongly recommends that you maintain performance benchmarks of your system before and after a migration.

vCompleted a recovery backup of your source system, at the previous release level.

Preparing the source system for the migration

This procedure assumes that you have:

v_ Loaded the new OS/400 version on your source system, and brought all existing objects and licensed programs to the new release level. Complete the procedure “Preparing the Current System” on page 18 through step 14.

v_ Set the system values, and print the current configuration.

v_ Completed a recovery backup of the source system at the new release level, and printed your latest system configuration information, including:

Latest system configuration list from hardware service manager

Latest device descriptions printout of the source system

Latest controller descriptions printout of the source system

Latest PTF level printout from the source system

v_ Run your source system at the new release level for two weeks, and completed a recovery backup. (Recommended)

v_ Have set up your new system, and/or created the new partition, including Operations Console setup (if selected in system order).

v_ Done your disk unit management (for example, manage disk protection and disk configuration). To do this, you can use the Work with Disk Units option from the Dedicated Service Tools display. For more information, see the manual Backup and Recovery, SC41-5304-05. A PDF version of this manual is available from the Information Center under Systems Management -> Backup, recovery, and availability -> Manuals and Redbooks.

© Copyright IBM Corp. 1997, 2001

31

Image 43
Contents ISeries 940x RISC-to-RISC Road Map Page ISeries 940x RISC-to-RISC Road Map Sixth Edition May Contents Iv iSeries 940x RISC-to-RISC Road Map V5R1 Who Should Read This Book ISeries 940x RISC-to-RISC Road Map, SA41-5155-05Conventions and Terminology Used in This Book V4R4M0 Prerequisite and related information Under the System Planning and Installation topicOperations Navigator How to send your commentsISeries 940x RISC-to-RISC Road Map, SA41-5155-05 ISeries 940x RISC-to-RISC Road Map V5R1 What is in this Road Map? Overview of RISC-to-RISC Upgrades and Data MigrationsUpgrade process flow What is an Upgrade?What is a Data Migration? How Long will the Upgrade Take?Hardware Investment for Upgrading Data migration process flow How Long will the Data Migration Take? Books to Use for Software Release UpgradesISeries 940x RISC-to-RISC Road Map V5R1 Planning Your Order for Upgrading or Data Migration Determining Your Upgrade NeedsHow to Gather Performance Information How to Gather Configuration InformationHardware Considerations Prerequisites Before Placing an OrderVersion 4 Software Items Other Software Related ItemsServices and Other Assistance System Configuration ConsiderationsModel-specific Considerations for Placing an Order Upgrading from a 4xx, 5xx, Sxx, or 6xx to a Migrating from a 5xx to an Who is Responsible for Ordering the Upgrade? Placing the Upgrade OrderUpgrading from a 6xx or 7xx to an Sending the Order to a Software Service Provider Other Than How to Get Help with the OrderSending the Order to IBM ISeries 940x RISC-to-RISC Road Map V5R1 Who is Responsible for Upgrading the System Procedure for an Upgrade RISC-to-RISCPreparing the Current System What to Do When the Hardware ArrivesThis is where you load the new operating system Preparing for System Assurance prior to hardware upgrade Print Disk Configuration Status of the installed system ISeries 940x RISC-to-RISC Road Map V5R1 System Assurance Checkpoint Managing your new system I/O resources Installing the Hardware for the RISC-to-RISC UpgradeInformation Center under System planning and installation ISeries 940x RISC-to-RISC Road Map V5R1 Change Description Label display appears Perform a normal IPL Performing a new system backupProcedure for an Upgrade RISC-to-RISC Systems Management Work management- Work Management Manuals Prerequisites for data migration Risc to Risc Procedure for a Data Migration RISC-to-RISCPreparing the source system for the migration Data migration RISC-to-RISC Procedure for a Data Migration RISC-to-RISC ISeries 940x RISC-to-RISC Road Map V5R1 ISeries Planning and Migration Services Appendix A. AS/400 Global ServicesISeries and AS/400 Data Migration Services Lpar Planning and Implementation ServicesPerformance Examinations Related Support ServicesAS/400 Solution Services Installation Services Consulting ServicesMidrange Enhanced Software Service Mress ISeries 940x RISC-to-RISC Road Map V5R1 IBM Http Server for AS/400 Appendix B. Considerations and SolutionsClustering and Logical Partitions SRC A900 2000 RecoveryOperations Console OptiConnect Integrated Netfinity ServerHow to Move Freed Database Files without New Members Command to restore the file. For a logical file, use PTF ISeries 940x RISC-to-RISC Road Map V5R1 Appendix D. Notices IBM TrademarksAppendix D. Notices ISeries 940x RISC-to-RISC Road Map V5R1 Rtvcfgsrc IndexISeries 940x RISC-to-RISC Road Map V5R1 How satisfied are you that the information in this book is Readers’ Comments We’d Like to Hear from YouBusiness Reply Mail Page SA41-5155-05