Table 4. Tasks and Responsibilities for the Upgrade Path (continued)

Checkoff

Task

Person Responsible

 

 

 

 

Save the system, just a system save

Customer

 

 

 

 

Run WRKHDWPRD command option 5 if OS/400 is on

Customer

 

the target system at the completion of the upgrade

 

 

 

 

 

Configure extra devices (DASD, for example)

Customer

 

 

 

 

Tune performance

Customer

 

 

 

 

Perform Redundant Array of Independent Disks (RAID)

Customer

 

and mirroring steps

 

 

 

 

 

Save the system, full save

Customer

 

 

 

 

Hold post-installation meeting

Customer Account Team Leader

 

 

 

 

Ensure IBM systems are accurate and updated

Marketing Representative

 

 

 

What to Do When the Hardware Arrives

When the hardware arrives, the customer should notify the hardware service representative and schedule a time for system assurance checkpoint prior to the hardware installation (MES upgrade).

Notes:

1.For customer install systems follow the instructions that came with your server to get set up. If you are replacing an existing system while preserving the original serial number, use the data migration section of this book.

2.The customer must have at least 64MB of memory or arrange to have additional memory installed before the upgrade can proceed. For more information on prerequisites prior to an upgrade, see the manual Software Installation, SC41-5120-05. A PDF version of this manual is available from the iSeries Information Center under System planning and installation ->

Hardware and software -> Software and licensed programs -> Install software.

Preparing the Current System

In this section, you will be asked to save your system several times. IBM strongly recommends that you save your system when instructed to do so. Saving your system allows you to have recovery data in case of disaster.

Approximately two weeks before the hardware service representative arrives, the customer should do the following:

__ 1. Acquire the preventive service planning information (see “Appendix C. Obtain the Latest Preventive Service Planning Information” on page 43) from electronic customer support, if available, or from the software service representative.

__ 2. For information pertaining to logical partitions, see the Logical Partitions topic under Systems Management in the iSeries Information Center. There are some specific steps to perform for upgrading a server with primary and secondary partitions installed.

__ 3. For considerations when upgrading to 5769-RD1 OnDemand, see “Appendix B. Considerations and Solutions” on page 39 for information on OnDemand.

18iSeries 940x RISC-to-RISC Road Map V5R1

Image 30
Contents ISeries 940x RISC-to-RISC Road Map Page ISeries 940x RISC-to-RISC Road Map Sixth Edition May Contents Iv iSeries 940x RISC-to-RISC Road Map V5R1 ISeries 940x RISC-to-RISC Road Map, SA41-5155-05 Who Should Read This BookConventions and Terminology Used in This Book V4R4M0 Under the System Planning and Installation topic Prerequisite and related informationHow to send your comments Operations NavigatorISeries 940x RISC-to-RISC Road Map, SA41-5155-05 ISeries 940x RISC-to-RISC Road Map V5R1 Overview of RISC-to-RISC Upgrades and Data Migrations What is in this Road Map?What is an Upgrade? Upgrade process flowHow Long will the Upgrade Take? What is a Data Migration?Hardware Investment for Upgrading Data migration process flow Books to Use for Software Release Upgrades How Long will the Data Migration Take?ISeries 940x RISC-to-RISC Road Map V5R1 Determining Your Upgrade Needs Planning Your Order for Upgrading or Data MigrationHow to Gather Configuration Information How to Gather Performance InformationOther Software Related Items Prerequisites Before Placing an OrderVersion 4 Software Items Hardware ConsiderationsSystem Configuration Considerations Services and Other AssistanceModel-specific Considerations for Placing an Order Upgrading from a 4xx, 5xx, Sxx, or 6xx to a Migrating from a 5xx to an Placing the Upgrade Order Who is Responsible for Ordering the Upgrade?Upgrading from a 6xx or 7xx to an How to Get Help with the Order Sending the Order to a Software Service Provider Other ThanSending the Order to IBM ISeries 940x RISC-to-RISC Road Map V5R1 Procedure for an Upgrade RISC-to-RISC Who is Responsible for Upgrading the SystemWhat to Do When the Hardware Arrives Preparing the Current SystemThis is where you load the new operating system Preparing for System Assurance prior to hardware upgrade Print Disk Configuration Status of the installed system ISeries 940x RISC-to-RISC Road Map V5R1 System Assurance Checkpoint Installing the Hardware for the RISC-to-RISC Upgrade Managing your new system I/O resourcesInformation Center under System planning and installation ISeries 940x RISC-to-RISC Road Map V5R1 Change Description Label display appears Performing a new system backup Perform a normal IPLProcedure for an Upgrade RISC-to-RISC Systems Management Work management- Work Management Manuals Procedure for a Data Migration RISC-to-RISC Prerequisites for data migration Risc to RiscPreparing the source system for the migration Data migration RISC-to-RISC Procedure for a Data Migration RISC-to-RISC ISeries 940x RISC-to-RISC Road Map V5R1 Lpar Planning and Implementation Services Appendix A. AS/400 Global ServicesISeries and AS/400 Data Migration Services ISeries Planning and Migration ServicesConsulting Services Related Support ServicesAS/400 Solution Services Installation Services Performance ExaminationsMidrange Enhanced Software Service Mress ISeries 940x RISC-to-RISC Road Map V5R1 Appendix B. Considerations and Solutions IBM Http Server for AS/400Integrated Netfinity Server SRC A900 2000 RecoveryOperations Console OptiConnect Clustering and Logical PartitionsHow to Move Freed Database Files without New Members Command to restore the file. For a logical file, use PTF ISeries 940x RISC-to-RISC Road Map V5R1 Appendix D. Notices Trademarks IBMAppendix D. Notices ISeries 940x RISC-to-RISC Road Map V5R1 Index RtvcfgsrcISeries 940x RISC-to-RISC Road Map V5R1 Readers’ Comments We’d Like to Hear from You How satisfied are you that the information in this book isBusiness Reply Mail Page SA41-5155-05