Graco EQ300C manual Shutting Down

Page 19

Shutting Down

1.When you have finished blasting, perform wash until all of the abrasive is flushed from the blast hose. See Using the Wash Feature, page 17.

2.Turn the selector valve to RINSE, and with the abrasive ball valve closed, continue to blast until water is cleared from the hose. This is to dry the inside of the hose for storage.

3.Open the abrasive ball valve, then open the dump valve until the pot pressure gauge reads 0 psi. Close the abrasive ball valve and dump valve.

NOTE: Short-term shutdown is now complete. If the until will be shut down for more than 24 hours, proceed to the next step.

4.Disconnect the abrasive ball valve cam-lock by removing the coupler pins and pulling the rings out and up to pull the two cams away from the groove.

Operation

5.Hold a bucket under the cam-lock coupler, then turn the selector valve to WASH. This will clean debris from the cam-lock coupler and gasket.

NOTE: Make sure the gasket is in place after the procedure.

NOTE: Be sure to catch the unspent abrasive that will be washed out of the panel plumbing and out of the groove fitting.

6.Turn the selector valve to FILL. This will help push the abrasive out through the abrasive hose.

7.Place a bucket under the abrasive hose. Slowly open and close the abrasive ball valve to flush abrasive material from the pot. Repeat several times. Once no abrasive material flows from the hose, close the abrasive ball valve.

NOTE: Estimate that a 5 gallon pail will be needed for each bag of abrasive still in the pot. Cover the buckets during storage so debris does not contaminate the abrasive.

334667B

19

Image 19
Contents EcoQuip Vapor Abrasive Blast System Important Safety InstructionsRelated Manuals ModelsDust and Debris Hazard Burn Hazard Metric OEM System GuidelinesCompressor Size and Hose Length Minimum ID Metric EQ300C and EQ600C System Component IdentificationKey DataTrak ControlsDataTrak see DataTrak Controls, Pressure Relief Procedure Operation Checklist Before StartingConnecting the Blast Hose and Air Hose Setting Up the Equipment 10 gal 200-500 lb Ti24824a 0 0 0 8 8 0 0 0 3 Blasting on Higher Surfaces Blasting TipsSteel Metering Valve SettingsGrit Size Blast Pressure Abrasive Dose Blast Angle General WoodUsing the Wash Feature Refilling the Pot with Abrasive Shutting Down Operation Winterizing the Equipment See Repairing the Main Air Regulator TroubleshootingProblem Cause Solution See Cleaning the Auto-Vent Valve,Intact. See Hose Schematic, See Setting Up the Equipment,See Repairing the Diaphragm Valve Procedure see Shutting Down,Setting Up the Equipment, Properly. See Hose Schematic,Metering Valve Settings, See Pressure Relief Procedure,If flushing does not solve the problem, see Checking for Leaks Troubleshooting ExamplesPneumatic Blast Control Circuit Perform Pressure Relief Procedure, Repairing the Main Air RegulatorRepair Flushing the Diaphragm Valve Perform the Pressure Relief Procedure, Repairing the Diaphragm ValveCleaning the Auto-Vent Valve Replace Battery Replacing the DataTrak BatteryApproved Batteries Replace Fuse Replacing the DataTrak FuseApproved Fuses DataTrak Part Series Letter Fuse Required EQ300C and EQ600C PartsPressure POT EQ300C and EQ600C Parts ListEnclosure Part Description Qty Enclosure Parts ListPressure Pot Pressure Pot Parts ListRef. Part Description Qty Hose Schematic Model Series Brakes Vapor Abrasive Blast Systems and AccessoriesEcoQuip Skid Systems EcoQuip Trailer SystemsModel Description Mobile/Skid UnitsTrailer Units ModelNozzles HosesModel Description Type Length Blast Control Common Spare Parts Other AccessoriesDimensions EQ300S Technical SpecificationsEQ600S Graco Information Graco Extended Warranty for EcoQuip Components