Graco EQ300C manual Repairing the Diaphragm Valve, Perform the Pressure Relief Procedure

Page 30

Repair

Repairing the Diaphragm Valve

NOTE: The diaphragm (17C127 – EQ300, 17C128

EQ600) can be replaced without removing the assembly from the panel. You will need an 8 mm Allen wrench for the EQ600S and a 6 mm for the

EQ300S.

1.Perform the Pressure Relief Procedure, page 8 .

2.Loosen all 4 Allen-head cap-bolts evenly and then remove them completely while supporting the canister of the diaphragm valve.

3.Replace the diaphragm (natural rubber compound) and hand-tighten it as far as possible to establish the alignment with the canister.

NOTE: There are two shims between the diaphragm and the actuator. Keep the shims and reuse them (they do not come with the replacement diaphragm). Do not cause any pre-load or torque on the diaphragm by over-tightening it in a misaligned position.

4.Insert all 4 Allen-head cap bolts but do not tighten them.

5.Apply more than 80 psi (5.5 Bar, MPa) air pressure to the regulator inlet to cause the piston to retract.

6.With the piston retracted, hand-tighten the 4 Allen-head cap bolts.

7.Release the air pressure.

8.Tighten the cap-bolts in an alternating pattern (see image below) to 80 +/- 8 in-lb (9 +/- 0.9 N•m). This will cause a slight bulge in the diaphragm between the canister and the stainless steel casting.

1 3

42

9.Test and confirm that the unit is working properly.

NOTE: This can be done using only water to charge the equipment – there is no need to use abrasive for this test.

30

334667B

Image 30
Contents Important Safety Instructions EcoQuip Vapor Abrasive Blast SystemModels Related ManualsDust and Debris Hazard Burn Hazard OEM System Guidelines MetricCompressor Size and Hose Length Minimum ID Metric System Component Identification EQ300C and EQ600CDataTrak Controls KeyDataTrak see DataTrak Controls, Pressure Relief Procedure Checklist Before Starting OperationConnecting the Blast Hose and Air Hose Setting Up the Equipment 10 gal 200-500 lb Ti24824a 0 0 0 8 8 0 0 0 3 Blasting Tips Blasting on Higher SurfacesWood Metering Valve SettingsGrit Size Blast Pressure Abrasive Dose Blast Angle General SteelUsing the Wash Feature Refilling the Pot with Abrasive Shutting Down Operation Winterizing the Equipment See Cleaning the Auto-Vent Valve, TroubleshootingProblem Cause Solution See Repairing the Main Air RegulatorProcedure see Shutting Down, See Setting Up the Equipment,See Repairing the Diaphragm Valve Intact. See Hose Schematic,See Pressure Relief Procedure, Properly. See Hose Schematic,Metering Valve Settings, Setting Up the Equipment,If flushing does not solve the problem, see Troubleshooting Examples Checking for LeaksPneumatic Blast Control Circuit Repairing the Main Air Regulator Perform Pressure Relief Procedure,Repair Flushing the Diaphragm Valve Repairing the Diaphragm Valve Perform the Pressure Relief Procedure,Cleaning the Auto-Vent Valve Replacing the DataTrak Battery Replace BatteryApproved Batteries Replacing the DataTrak Fuse Replace FuseApproved Fuses DataTrak Part Series Letter Fuse Required Parts EQ300C and EQ600CEQ300C and EQ600C Parts List Pressure POTEnclosure Enclosure Parts List Part Description QtyPressure Pot Parts List Pressure PotRef. Part Description Qty Hose Schematic EcoQuip Trailer Systems Vapor Abrasive Blast Systems and AccessoriesEcoQuip Skid Systems Model Series BrakesModel Mobile/Skid UnitsTrailer Units Model DescriptionHoses NozzlesModel Description Type Length Blast Control Other Accessories Common Spare PartsDimensions Technical Specifications EQ300SEQ600S Graco Extended Warranty for EcoQuip Components Graco Information