Mounting Bolt Installation (If Required)
| 1 |
|
| 2 |
|
| 3 |
|
6 in. |
|
|
(152 mm) |
|
|
| 4 | CFS485N |
|
| |
|
| CFS485N |
1 | Base Frame |
|
2 | Bolt |
|
3 | Washer |
|
4 | Anchor Bolt/Plug |
|
Figure 28
After the concrete has cured and the anchors are installed, proceed as follows:
1.Place the
2.Place the
Installation
3.Put bolts through the machine in the anchors and fasten them. (For the 18, 25, and 35 models, the diameter of the bolt must be minimum
4.To level machine, fill the spaces between the machine base and floor with machinery grout. Grout completely under all frame members.
Remove front and rear panels to gain access to all frame members. Force grout under the machine base until all voids are filled.
5.Remove the spacers carefully, allowing the machine to settle into the wet grout.
6.Position washers and locknuts on machinery anchor bolts and
7.After the grout is completely dry, tighten the locknuts by even increments – one after the other – until all are tightened evenly and the machine is fastened securely to the floor.
8.Remove the four red transport brackets which secure the moving components of the machine during shipping. Refer to Figures 29, 31 and 32 for typical transport bracket locations.
9001000 | © Copyright, Alliance Laundry Systems LLC – DO NOT COPY or TRANSMIT | 41 |