1.Reassembly for the MLS-410 2 Door/2-Way Tilt Steam Model Dryer...

Lift the tumbler (basket) section onto the base.

a.2-Way tilting dryers have four (4) tilting pistons, one (1) located in each corner of the dryer base. On the top of each tilting piston is a clevis blocks. Use the four (4) 1/2 x 1-1/4” hex head bolts and lock washers (supplied with the dryer) to secure each clevis block to the bottom of the tumbler (basket) section.

Refer to Tilting Piston Reconnection View on page 29.

b.Both the 2-inch (5.08 cm) steam supply line and the 1-1/4” (3.18 cm) condensate return line unions are disconnected when the dryer is shipped in two (2) pieces. The steam supply lines are located in the right hand side of the dryer base. Insert both union halves up through the holes in the bottom of the tumbler (basket) section. Connect the two (2) union halves and retighten.

IMPORTANT: THE FLEX HOSE MUST NOT BE KINKED.

Refer to Steam Flex Hose Union Reconnection View on page 29.

c.The air lines are disconnected when the dryer is shipped in two (2) pieces. The air lines are located in the right side of the dryer base. Insert the air lines through the hole on the bottom of the tumbler (basket) section. Reconnect the 1/4” brass poly connector.

d.There are three (3) electrical reconnections...

1)The plug and cable connections are located in the right hand side of the dryer base. These must be lifted up and reconnected into the mating sockets located at the bottom right hand side of the tumbler (basket) section.

2)The drive motor power cable must be lifted up and reconnected into the drive motor in the right hand side of the tumbler (basket) section.

IMPORTANT: THE RECONNECTED ELECTRICAL CABLES MUST HAVE ENOUGH SLACK IN THEM TO ALLOW THE DRYER TO TILT FREELY IN BOTH DIRECTIONS.

e.Reattach The Tilt Guard Panel...

1)Use the 1/4-20 x 3/8” hex head bolts and lock washers (supplied with the dryer) to secure the top of the front tilt guard into the bottom of the front of the tumbler (basket) section.

2)Use the 1/4-20 x 3/8” hex head bolts and lock washers (supplied with the dryer) to secure the top of the rear tilt guard to the bottom of the rear of the tumbler (basket) section.

3)Use the 1/4-20 self-tapping screws (supplied with the dryer) to secure the right side tilt guards and left side tilt guards.

Refer to Tilt Guard Panel Reconnection View on page 29.

28

Image 32
Contents What do YOU do if YOU Smell GAS QUE Faire SI Vous Sentez UNE Odeur DE GAZFor Your Safety Pour Votre SécuritéFor Your Safety Page Table of Contents Cleaning Adjustments Lubrication Air Blower Drive SystemML-410 Reference Guide Page ML-410 Operator CONTROLS/INDICATORS ML-410 Machine Operational SummaryJOG Forward/Reverse Push-Buttons END of CYCLE/AIR JETAIR JET ML-410 Machine Operation Troubleshooting InformationEND of CYCLE/HEATER Fault Indicator If this selection does not operate Unload TiltedLoad Tilted DRY ONE or Both Burners do not IgniteGAS Pressure Important InformationONE Burner will not Ignite AT the Beginning of a Cycle ONE Burner will not Ignite During a Drying CycleFront Level Switch Rear Level Switch System Ladder DiagramTumbler Temperature and HI-LIMIT Information Optional Sprinkler Control Signals Section Safety Precautions What to do if YOU Smell GASStandards Specifications and Dimensions Dimensions 410 Tilting Clearance Allow AncesML-410 1 Door/2-Way Tilt ML-410 1 Door/2-Way Tilt MLS-410 1 Door/2-Way Tilt ML-410 1 Door/2-Way Tilt With Inlet Air Adapter Installation Procedures Reassembly of DryerMLG-410 1 Door/Forward Tilt with Sprinkler Important the Flex Hose Must not be Kinked MLG-410 1 Door/Forward Tilt With Sprinkler MLS-410 2 Door/2-Way Tilt Refer to Tilting Piston Reconnection View on MLS-410 2 Door/2-Way Tilt Fresh AIR Supply Requirements Exhaust Requirements Compressed AIR Supply System Page Electrical Information Optional Automatic Piston Operated Load/Unload DoorsOptional Sprinkler Valve Electrical RequirementsElectrical Service Specifications MLG-410 Gas MLS-410 SteamMain Grounding GAS Information Technical Gas Data Gas Specifications Type of GasPiping /Connections Page Steam Information Steam Requirements High PressurePage Air Connections Air connection to system --- 1/8-inch N.P.T Steam Damper Air System ConnectionsAir Requirements Steam Damper System Operation Steam Damper Air Piston Flow Control Operation Adjustment Water Supply Connection for Optional Sprinkler SystemPreoperational Tests Natural GAS Heat Circuit Operational Test a. Gas ModelsPreparation for OPERATION/START-UP Basket CoatingShut Down Instructions Service PartsReturning Warranty Cards Returning Warranty PartsPage Routine Maintenance CleaningMonthly Adjustments LubricationComponent System Descriptions Tumbler Basket Drive SystemSafety Devices Tumbler Basket Manual Reset Hi-Limit Safety ThermostatTumbler Basket AIR Blower Drive SystemSail Switches for Gas Dryers Only Steam Damper Actuator System Optional Sprinkler System Components Optional Sprinkler Circuit ComponentsRefer to the Dryer Nameplate for voltage rating information ML-410 Sprinkler Option Temperature Controller Settings ADC 113128 1- 03/13/00-25