American Dryer Corp ML-410 manual Fresh AIR Supply Requirements

Page 34

B. FRESH AIR SUPPLY REQUIREMENTS

When the dryer is operating, it draws in room air, heats it, passes this air through the tumbler (basket), and exhausts it out of the building. Therefore, the room air must be continually replenished from the outdoors. If the make-up air is inadequate, drying time and efficiency will be adversely affected. Ignition problems and sail switch “fluttering” problems may result, as well as premature motor failure from overheating.

Air supply (make-up air) must be given careful consideration to assure proper performance of each dryer. An unrestricted source of air is necessary for each dryer. An airflow of 9,200 cfm (cubic feet per minute) - 260.52 cmm (cubic meters per minute) - must be supplied to each gas dryer and 12,000 cfm (cubic feet per minute) -

339.80cmm must be supplied to each steam dryer. As a general rule, an unrestricted air entrance from the outdoors (atmosphere) of a minimum of 12 square feet (1.15 square meters) is required for each gas dryer and a minimum of 14 square feet (1.30 square meters) is required for each steam dryer.

To compensate for the use of registers or louvers used over the openings, this make-up air area must be increased by approximately thirty-three percent (33%). Make-up air openings should not be located in an area directly near where exhaust vents exit the building.

It is not necessary to have a separate make-up air opening for each dryer. Common make-up air openings are acceptable. However, they must be set up in such a manner that the make-up air is distributed equally to ALL the dryers.

Allowances must be made for remote or constricting passageways or where dryers are located at excessive altitudes or predominantly low pressure areas.

IMPORTANT: Make-up air must be provided from a source free of dry cleaning solvents fumes. Make-up air that is contaminated by dry cleaning solvent fumes will result in irreparable damage to the motors and other dryer components.

NOTE: Component failure due to dry cleaning solvent fumes will VOID THE WARRANTY.

1.Optional Inlet Air Adapter

The MLG-410 dryer may be built with the inlet air adapter option. This option allows ALL of the dryers’ inlet air to be ducted from the outdoors directly to the dryer.

This option consists of a sheet metal box located on top of the dryer with two (2) 30-inch (76.2 cm) diameter duct collars on top. (Refer to the illustration on page 22 for the location and dimensions of the inlet air adapter.)

Use two (2) 30-inch (76.2 cm) diameter flexible hoses to connect the 30-inch (76.2 cm) collars to the outdoors. Allow enough slack in the flexible hoses so that the dryer can tilt, without restriction.

30

Image 34
Contents What do YOU do if YOU Smell GAS QUE Faire SI Vous Sentez UNE Odeur DE GAZFor Your Safety Pour Votre SécuritéFor Your Safety Page Table of Contents Cleaning Adjustments Lubrication Air Blower Drive SystemML-410 Reference Guide Page ML-410 Operator CONTROLS/INDICATORS ML-410 Machine Operational SummaryJOG Forward/Reverse Push-Buttons END of CYCLE/AIR JETEND of CYCLE/HEATER Fault Indicator ML-410 Machine Operation Troubleshooting InformationAIR JET Load Tilted Unload TiltedIf this selection does not operate DRY ONE or Both Burners do not IgniteGAS Pressure Important InformationONE Burner will not Ignite AT the Beginning of a Cycle ONE Burner will not Ignite During a Drying CycleTumbler Temperature and HI-LIMIT Information System Ladder DiagramFront Level Switch Rear Level Switch Optional Sprinkler Control Signals Section Safety Precautions What to do if YOU Smell GASStandards Specifications and Dimensions Dimensions 410 Tilting Clearance Allow AncesML-410 1 Door/2-Way Tilt ML-410 1 Door/2-Way Tilt MLS-410 1 Door/2-Way Tilt ML-410 1 Door/2-Way Tilt With Inlet Air Adapter Installation Procedures Reassembly of DryerMLG-410 1 Door/Forward Tilt with Sprinkler Important the Flex Hose Must not be Kinked MLG-410 1 Door/Forward Tilt With Sprinkler MLS-410 2 Door/2-Way Tilt Refer to Tilting Piston Reconnection View on MLS-410 2 Door/2-Way Tilt Fresh AIR Supply Requirements Exhaust Requirements Compressed AIR Supply System Page Optional Sprinkler Valve Electrical InformationOptional Automatic Piston Operated Load/Unload Doors Electrical RequirementsElectrical Service Specifications MLG-410 Gas MLS-410 SteamMain Grounding GAS Information Technical Gas Data Gas Specifications Type of GasPiping /Connections Page Steam Information Steam Requirements High PressurePage Air Requirements Steam Damper Air System ConnectionsAir Connections Air connection to system --- 1/8-inch N.P.T Steam Damper System Operation Steam Damper Air Piston Flow Control Operation Adjustment Water Supply Connection for Optional Sprinkler SystemPreoperational Tests Natural GAS Heat Circuit Operational Test a. Gas ModelsPreparation for OPERATION/START-UP Basket CoatingShut Down Instructions Service PartsReturning Warranty Cards Returning Warranty PartsPage Routine Maintenance CleaningMonthly Adjustments LubricationComponent System Descriptions Tumbler Basket Drive SystemTumbler Basket Safety DevicesTumbler Basket Manual Reset Hi-Limit Safety Thermostat AIR Blower Drive SystemSail Switches for Gas Dryers Only Steam Damper Actuator System Optional Sprinkler System Components Optional Sprinkler Circuit ComponentsRefer to the Dryer Nameplate for voltage rating information ML-410 Sprinkler Option Temperature Controller Settings ADC 113128 1- 03/13/00-25