6.Make a complete operational check of ALL safety-related circuits (i.e., lint drawer switch and sail switches on Gas Models).

7.A reversing tumbler (basket) should never be operated with less than a 250-pound (113.39 kg) load (dry weight). The size of the load will affect the coast-down and dwell (stop) times. The tumbler (basket) must come to a complete stop before starting in the opposite direction. For automatic (mode) cycle only, the spin and stop times are not adjustable and have been preprogrammed into the microprocessor controller (computer) for a 2-minute spin time and a 7-second dwell (stop) time.

BASKET COATING

The tumbler (basket) is treated with a protective coating. We suggest dampening old garments or cloth material with a solution of water and non-flammable mild detergent and tumbling them in the tumbler (basket) to remove this coating.

8.Each dryer should be operated through one (1) complete cycle to assure that no further adjustments are necessary and that ALL components are functioning properly.

9.Microprocessor Controller (computer) programs/selections...

a.Each microprocessor controller (computer) has been preprogrammed by the factory with the most commonly used program (parameter) selections. If computer programming changes are required, refer to the Computer Programming Manual which was shipped with the dryer.

J.PREPARATION FOR OPERATION/START-UP

The following items should be checked before attempting to operate the dryer:

1.Read ALL “CAUTION,” “WARNING,” and “DIRECTION” labels attached to the dryer.

2.Check incoming supply voltage to be sure that it is the same as indicated on the dryer data label affixed behind the right control box door. In the case of 208 VAC or 230 VAC for dryers with sprinkler option, verify single-phase (1ø) voltage is correct. THE SUPPLY VOLTAGE MUST MATCH THE ELECTRICAL

SERVICE EXACTLY.

3.GAS MODELS --Check to assure that the dryer is connected to the type of heat/gas indicated on the dryer data label.

4.GAS MODELS --the sail switch damper assembly was installed and adjusted at the factory prior to shipping. However, each sail switch adjustment must be checked to assure that this important safety control is functioning.

5.GAS MODELS --be sure that ALL gas shut-off valves are in the open position.

6.Be sure ALL side and base panels are on the dryer.

7.Check ALL service doors to assure that they are closed and secure.

8.Be sure the lint drawer is securely in place.

48

Image 52
Contents What do YOU do if YOU Smell GAS QUE Faire SI Vous Sentez UNE Odeur DE GAZFor Your Safety Pour Votre SécuritéFor Your Safety Page Table of Contents Cleaning Adjustments Lubrication Air Blower Drive SystemML-410 Reference Guide Page ML-410 Operator CONTROLS/INDICATORS ML-410 Machine Operational SummaryJOG Forward/Reverse Push-Buttons END of CYCLE/AIR JETEND of CYCLE/HEATER Fault Indicator ML-410 Machine Operation Troubleshooting InformationAIR JET Load Tilted Unload TiltedIf this selection does not operate DRY ONE or Both Burners do not IgniteGAS Pressure Important InformationONE Burner will not Ignite AT the Beginning of a Cycle ONE Burner will not Ignite During a Drying CycleTumbler Temperature and HI-LIMIT Information System Ladder DiagramFront Level Switch Rear Level Switch Optional Sprinkler Control Signals Section Safety Precautions What to do if YOU Smell GASStandards Specifications and Dimensions Dimensions 410 Tilting Clearance Allow AncesML-410 1 Door/2-Way Tilt ML-410 1 Door/2-Way Tilt MLS-410 1 Door/2-Way Tilt ML-410 1 Door/2-Way Tilt With Inlet Air Adapter Installation Procedures Reassembly of DryerMLG-410 1 Door/Forward Tilt with Sprinkler Important the Flex Hose Must not be Kinked MLG-410 1 Door/Forward Tilt With Sprinkler MLS-410 2 Door/2-Way Tilt Refer to Tilting Piston Reconnection View on MLS-410 2 Door/2-Way Tilt Fresh AIR Supply Requirements Exhaust Requirements Compressed AIR Supply System Page Electrical Information Optional Automatic Piston Operated Load/Unload DoorsOptional Sprinkler Valve Electrical RequirementsElectrical Service Specifications MLG-410 Gas MLS-410 SteamMain Grounding GAS Information Technical Gas Data Gas Specifications Type of GasPiping /Connections Page Steam Information Steam Requirements High PressurePage Air Requirements Steam Damper Air System ConnectionsAir Connections Air connection to system --- 1/8-inch N.P.T Steam Damper System Operation Steam Damper Air Piston Flow Control Operation Adjustment Water Supply Connection for Optional Sprinkler SystemPreoperational Tests Natural GAS Heat Circuit Operational Test a. Gas ModelsPreparation for OPERATION/START-UP Basket CoatingShut Down Instructions Service PartsReturning Warranty Cards Returning Warranty PartsPage Routine Maintenance CleaningMonthly Adjustments LubricationComponent System Descriptions Tumbler Basket Drive SystemSafety Devices Tumbler Basket Manual Reset Hi-Limit Safety ThermostatTumbler Basket AIR Blower Drive SystemSail Switches for Gas Dryers Only Steam Damper Actuator System Optional Sprinkler System Components Optional Sprinkler Circuit ComponentsRefer to the Dryer Nameplate for voltage rating information ML-410 Sprinkler Option Temperature Controller Settings ADC 113128 1- 03/13/00-25