Airstream PNEG-343 service manual Series Batch Timer Settings, Full Heat Dry & Cool

Page 23

DRYER START UP & OPERATION

1300 SERIES BATCH TIMER SETTINGS

 

 

 

Full Heat

 

 

Dry & Cool

 

 

 

Fan & Burner Switche(s) on Manual

Fan(s) on Manual

Burner(s) on Auto

 

 

 

 

 

 

 

 

 

 

Initial

Moisture

Approx.

 

 

 

Approx.

 

 

 

Moisture

Removed

Dry Time

Dry

Cool

Unload*

Dry Time

Dry

Cool

Unload*

17%

2 pts.

16 min.

6 min.

0

10 min.

18 min.

18 min.

18 min.

10 min.

18%

3 pts.

21 min.

11 min.

0

10 min.

24 min.

24 min.

18 min.

10 min.

19%

4 pts.

26 min

16 min

0

10 min.

30 min

30 min

18 min

10 min.

20%

5 pts.

31.5 min.

21.5 min.

0

10 min.

35 min.

35 min.

18 min.

10 min.

21%

6 pts.

37 min.

27 min.

0

10 min.

40 min.

40 min.

18 min.

10 min.

22%

7 pts.

41.5 min.

31.5 min.

0

10 min.

45 min.

45 min.

18 min.

10 min.

23%

8 pts.

47 min.

37 min.

0

10 min.

50 min.

50 min.

18 min.

10 min.

24%

9 pts.

51 min.

47 min.

0

10 min.

55 min.

55 min.

18 min.

10 min.

25%

10 pts.

54 min.

44 min.

0

10 min.

60 min.

60 min.

18 min.

10 min.

26%

11 pts.

58 min.

48 min.

0

10 min.

65 min.

65 min.

18 min.

10 min.

27%

12 pts.

62 min.

52 min.

0

10 min.

70 min.

70 min.

18 min.

10 min.

28%

13 pts.

66.5 min.

56.5 min.

0

10 min.

75 min.

75 min.

18 min.

10 min.

29%

14 pts.

71.5 min.

61.5 min.

0

10 min.

80 min.

80 min.

18 min.

10 min.

30%

15 pts.

76 min.

66 min.

0

10 min.

85 min.

85 min.

18 min.

10 min.

31%

16 pts.

81 min.

71 min.

0

10 min.

90 min.

90 min.

18 min.

10 min.

32%

17 pts.

86 min.

76 min.

0

10 min.

95 min.

95 min.

18 min.

10 min.

33%

18 pts.

91 min.

81 min.

0

10 min.

100 min.

100 min.

18 min.

10 min.

34%

19 pts.

96 min.

86 min.

0

10 min.

105 min.

105 min.

18 min.

10 min.

35%

20 pts.

100 min.

90 min.

0

10 min.

110 min.

110 min.

18 min.

10 min.

These are approximate starting points.

*Set unload meter roll high speed setting to 999. If unload equipment cannot adequately keep up, lower the speed setting and add time to the unload timer setting to completely unload the batch. In full heat mode, the time added to the unload timer will need to be substracted from the dry timer. If fan is on auto and does not run during unload, set cool timer to 25 minutes.

New unload time calculation = present unload time new dial setting

1000

Example

13.75= 11 800 1000

23

Image 23
Contents Ryer Operation Page Table of Contents Series Dryer Operation and ServiceWarranty Careful Operator Is the Best Insurance Against AN Accident Safety FirstSafety Alert Symbol Safety Alert DecalsSafety Alert Decals Keep the Dryer Clean Do not Allow Fine Safety PrecautionsInformation regarding dryer operation Moisture Control SwitchDryer Control Panel Moisture Control ThermostatFAN Switches Control Power SwitchDrying Mode Switch Load Auger SwitchDryer Power Stop Switch Dryer Power Start SwitchTurning on Electronic Monitoring Control System Setting the DRY, Cool Batch and Unload TimersSetting the OUT Grain Timer Electronic Monitoring Control SystemUtilizing Bushel Counter Setting the Load Unload DelaysDryer Safety Circuit Safety Circuit Shutdown Messages PRE Season Inspection Dryer PRE Start ChecksMetering Roll Operation TWO Speed OperationLoad Auger ONE Speed OperationBurner Test Fire Burner SafetyEmergency Staged Batch CheckDryer Shutdown Continuous Flow Operation Continuous Flow and Continuous Batch Start UP ProcedureTurn the control power switch to on Dryer Start UPFull Heat Series Continuous Flow Metering Roll SettingsDryer Start UP & Operation Dry & Cool Continuous Flow Metering Roll SettingsStaged Batch Operation Matically shut down during the cooling and unloading cycles Staged Batch FAN & Heater Switch SettingsFull Heat Dry & Cool Series Batch Timer SettingsSeries Staged Batch Timer Settings Series Service Guide Lube Procedures ServiceSeasonal Inspection and Service Insulation Class Consistency Type Grease Frame Type Suggested LubricantsClearance Holes FAN Propellor Removal and InstallationThreaded Bushing Holes FAN Motor Removal and Installation Heater Parts Removal and Installation Main Controls Metering Roll ServicingService Tool HOW to Determine a Metering Roll ProblemHOW to Clear a Jammed Metering Roll Series Wiring Diagrams INPUT/OUTPUT Board Terminal Identification Series Wiring to Control BOX Series Control Wiring Series Safety Wiring Diagram Series Front Panel Internal Wiring Series Front Panel External Wiring Dryer FAN can Control Wiring Series 220 Volt Single Phase Control Wiring Series 220 Volt 3 Phase Power Wiring Series 440 Volt 3 Phase Power Wiring Problem Possible Cause Trouble Analysis ProcedureDisplay shows Burner 1, 2 or 3 Warning Flame May not be turning. The air switch may need adjustment Problem Possible Cause Trouble Analysis Procedure Change the marquee on the LCD dis- play Press the enter button when desired setting is reachedQuick Reference Guide Page