•If no, check associated:
•Switch and Wiring
•Check wiring back to the Base Electrical Junction Box
•Check PLC (Programmable Logic Controller)
•Refer to Wiring Diagrams:
•Main Electrical Panel Diagram
•Base Electrical Junction Box Wiring Diagram.
•Retest; verify that the signal is operational.
3b) Place the
•Actuate the Rear Down switch by hand.
•Have someone verify that PLC (Programmable Logic Controller) input L.E.D. (light emitting diode) #12 lights when the switch actuator is down, and is OFF when the actuator is up.
•Does L.E.D. (light emitting diode) #12 come “ON” when the switch is down?
•If yes, wiring is OK.
•Check switch, actuator placement and tilt actuation.
NOTE: If actuator is at a 90° or greater angle with the base, the actuator will damage if machine is lowered.
•If no, check associated:
•Switch and Wiring.
•Check wiring back to the Base Electrical Junction Box.
•Check PLC (Programmable Logic Controller).
•Refer to Wiring Diagrams:
•Main Electrical Panel Diagram
•Base Electrical Junction Box Wiring Diagram.
•Retest; verify that the signal is operational.
84