Maytag W10240584B Closet installation dryer only, Cabinet installation dryer only, Back view

Page 6

Back view:

Closet installation (dryer only):

 

 

61/4"

 

 

 

(159 mm)

 

 

 

 

34" recommended

3"

 

 

(76 mm)

 

Electric

(864 mm)

 

48 in.2

18" min.

 

(310 cm2)

 

 

 

 

(457 mm)

 

 

281/8"

 

 

 

(715 mm)

 

 

24 in.2

 

 

 

31/2"

4"

3"

(155 cm2)

 

(89 mm)

(102 mm)

(76 mm)

 

 

 

 

 

 

1"

Back exhaust

1"

(25 mm)

 

vent location

(25 mm)

 

 

Cabinet installation (dryer only):

 

14"

 

 

(358 mm)

 

NOTE: Most installations require a minimum of 5" (127 mm) clearance behind dryer for exhaust vent with elbow. See “Venting Requirements.”

IMPORTANT: Do not operate, install, or store dryer where

it will be exposed to water, weather, or at temperatures below 45° F (7° C). Lower temperatures may cause dryer not to shut off at end of automatic sensor cycles, resulting in longer drying times.

Installation spacing for recessed area or closet installation

All dimensions show recommended spacing allowed, with tested spacing of 0" (0 mm) clearance on sides and rear.

■■ Additional spacing should be considered for ease of installation and servicing.

7" (178 mm)

18"

(460 mm)

■■ Additional clearances might be required for wall, door, and floor moldings.

■■ Additional spacing should be considered on all sides of the dryer to reduce noise transfer.

■■ For closet installation, with a door, minimum ventilation openings in the top and bottom of the door are required.

4"

(102 mm)

1"

1" (25 mm)

Louvered doors with equivalent ventilitation openings are acceptable.

■■ Companion appliance spacing should also be considered.

(25 mm)

6

Image 6
Contents Table of Contents Dryer Safety Your safety and the safety of others are very importantWhat to do if YOU Smell GAS Tools needed for all installations Installation Requirements Tools and PartsTools needed for gas installations Parts supplied steam modelsYou will need Dryer DimensionsLocation Requirements Front viewCloset installation dryer only Cabinet installation dryer onlyBack view Electric Dryer Power HOOKUP- Canada only Electrical RequirementsGAS Type GAS Dryer Power HookupGAS Supply Requirements Natural GasBurner Input Requirements GAS Supply LineGAS Supply Connection Requirements Dryer GAS PipeInstallation Instructions Venting REQUiREMENTSOptional exhaust installations Alternate exhaust installations for close clearanceChoose your exhaust installation type Plan Vent SystemINStall Vent System Install Leveling LegsMake GAS Connection Connect Inlet HoseAttach long hose to dryer fill valve and tighten coupling Attach long hose to Y connector and tighten couplingsTighten couplings Turn on cold water faucetConnect vent Level dryerTroubleshooting Complete InstallationChecklist Door ReversalSécurité de la sécheuse Votre sécurité et celle des autres est très importanteQUE Faire Dans LE CAS D’UNE Odeur DE GAZ Outils nécessaires pour toutes les installations Exigences Dinstallation Outillage ET PiècesOutils nécessaires aux installations au gaz Pièces fournies tous les modèlesIl vous faudra Exigences DemplacementDimensions DE LA Sécheuse Vue de faceVue arrière Installation dans un placard sécheuse seulement Cest à lutilisateur quincombe la responsabilité de Installation sous comptoir personnalisée sécheuse seulementSpécifications Électriques Toutes les sécheusesConservez CES Instructions Raccordement Dune Sécheuse À GAZInstructions DE Liaison À LA Terre Type DE GAZExigences Concernant LE Raccordement AU GAZ Conversion pour lalimentation au propaneCanalisation DE GAZ Caractéristiques Dalimentation DU BrûleurInstructions Pour LInstallation Exigences ConcernantLévacuation Installations dévacuation facultatives Planification DU Système DévacuationDispositions spéciales pour les maisons mobiles Tableau des systèmes dévacuation Installation DU Circuit DévacuationInstaller le clapet dévacuation Raccorder le conduit dévacuation au clapetInstallation DES Pieds DE Nivellement Raccordement AU GAZSerrer les raccords Raccordement DU Tuyau Darrivée DeauFixer le tuyau court et le raccord en Y Fixer le long tuyau au raccord en Y et serrer les raccordsRaccorder le conduit dévacuation à la bouche dévacuation 16. Déplacer la sécheuse à son emplacement finalRaccordement DU Conduit Dévacuation Ouvrir le robinet deau froide17. Régler laplomb de la sécheuse Achever Linstallation Liste DE VérificationRéglage DE Laplomb DE LA Sécheuse Serrer et ajuster les pieds de nivellementInversion DE LA Porte DépannageW10240584B W10240585B-SP