Sterling SSPET 5 operating instructions Removal, Installation

Page 40

SM4-630

SSPET5

Removal

 

 

 

 

 

Open the tension ring (A) and

 

 

 

 

 

remove the hopper loader lid (B).

 

 

 

 

 

Open the tension ring (C) and re-

B

 

 

 

 

move cleaning unit (D).

 

 

 

 

 

 

 

 

 

Release clamping devices of the

A

filter cartridges.

D

 

 

 

Remove the filter cartridges (E)

 

 

 

C

from the intermediate platform.

E

Clean the filter cartridges (E) from

 

 

 

 

 

the inside out by means of com-

 

 

 

 

 

pressed air.

 

 

 

 

 

or

 

 

 

 

 

Replace the filter cartridges by new

 

 

 

 

 

ones.

 

 

 

 

 

 

 

 

 

 

 

SSPET5

Installation

Insert filter cartridges (E) into the opening of the intermediate platform.

F

Make sure that the sealing pad is tightly fitted between filter

cartridges and intermediate platform.

Mount clamping devices of the filter cartridges.

Mount the cleaning unit (D) and the tension ring (C).

Mount the hopper loader lid (B) and the tension ring (A).

&

Order number filter cartridges (= 4 pcs.): ID 83379

 

 

Install the unit.

Maintenance 39

Image 40
Contents Sspet Sterling Material ProcessingParts and Service Department Technical service Telephone 800 Edition 02/01 Sterling order confirmation noSSPET5 Table of contents Maintenance Technical data Parts list AccessoriesSafety instructions Safety instructionsSSPET5 Explanations and information For your safety SSPET5 SSPET5 For the operating safety of the equipment Assembly instructions Assembly Assembly SM4-630 Mounting the suction pipe MV Electrical connection Installation of the flap switch signal line Installation of the signal line of the SKW optionalSSPET5 Compressed-air supply Functional description General Controller SSE SSPET5 Controller SSP Putting into operation Checking the pipe system If the conditions points 3 + 4 are not met Adjusting the suction pipesIf the conditions points 3 + 4 are met Setting the controller SSE Setting the conveying timeTurbine is running but no material is being conveyed Conveying capacity is too lowSetting the line clear time Change-over keySetting the controller SSP Setting the time intervalAlarm Messages displayed on the controller SSE Initial conveying operationsSSPET5 Alarm Messages displayed on the controller SSP Switching off the unitMaintenance SSPET5 Maintenance intervals Servicing the conveyor Installation RemovalChanging the sealing ring of the outlet flap Adjusting the flap switch Replacing carbon brushes at turbine Installation Technical data Optional FeaturesTechnical data Basic VersionDimension Sheet Parts list SSPET5 Pos Order no Designation Accessories