Sterling SSPET 5 Adjusting the suction pipes, If the conditions points 3 + 4 are not met

Page 29

SSPET5

4.2. Adjusting the suction pipes

The suction pipes have to be adjusted exactly to ensure troublefree operation.

1. Set the suction pipes to their home position.

&

At home position the inner pipe of the suction pipe protrudes about 120-160 mm (4.72-6.30 in) from the outer pipe at the top end.

2. Start a conveying operation.

Connect the unit to mains supply by the device plug.

3. Observe the flexible hose at the suction pipe.

The flexible hose must not show any pulsating movement.

4. Observe the flexible hose at the separator.

The conveying hose must only move during in-feed.

If the conditions (points 3 + 4) are not met:

Pull the inner pipe further out of the outer pipe until there is no more jerky convey- ance.

If the conditions (points 3 + 4) are met:

Push the inner pipe slowly into the outer pipe until pulsating of the flexible hose or shock conveyance occurs.

Now pull the inner pipe slightly back again until the hose stop pulsating.

Select a setting between the two pipes to ensure that enough air can flow into the material pipe.

Once you have reached a satisfactory conveying result turn the wing screw at the suction pipe tight.

SM4-630

Putting into operation 28

Image 29
Contents Sterling Material Processing SspetParts and Service Department Telephone 800 Edition 02/01 Sterling order confirmation no Technical serviceSSPET5 Table of contents Technical data Parts list Accessories MaintenanceSafety instructions Safety instructionsSSPET5 Explanations and information For your safety SSPET5 SSPET5 For the operating safety of the equipment Assembly instructions Assembly Assembly SM4-630 Mounting the suction pipe MV Electrical connection Installation of the signal line of the SKW optional Installation of the flap switch signal lineSSPET5 Compressed-air supply Functional description General Controller SSE SSPET5 Controller SSP Putting into operation Checking the pipe system If the conditions points 3 + 4 are met Adjusting the suction pipesIf the conditions points 3 + 4 are not met Setting the conveying time Setting the controller SSETurbine is running but no material is being conveyed Conveying capacity is too lowChange-over key Setting the line clear timeSetting the time interval Setting the controller SSPInitial conveying operations Alarm Messages displayed on the controller SSESSPET5 Switching off the unit Alarm Messages displayed on the controller SSPMaintenance SSPET5 Maintenance intervals Servicing the conveyor Removal InstallationChanging the sealing ring of the outlet flap Adjusting the flap switch Replacing carbon brushes at turbine Installation Optional Features Technical dataTechnical data Basic VersionDimension Sheet Parts list SSPET5 Pos Order no Designation Accessories