2.4. Compressed-air supply

For operating the cleaning unit, a compressed-air supply is necessary.

L

F

Depressurize compressed-air supply lines which must be opened.

Compressed air must be dewatered, dustfree and oilfree.

Install a maintenance unit if required.

Adjust pressure to a max. value of 6 bar (87.02 PSI) (system overpressure).

Check compressed-air piping for correct installation and assembly.

Check fittings, length and quality of the hose connections for agreement with re- quirements.

The operating pressure is 5-6 bar (72.52-87.02 PSI) (system overpressure). Check the compressed-air supplied by the plant’s supply network.

Adjust compressed-air pressure to 5-6 bar (72.52-87.02 PSI) (system overpressure).

Connect the unit to the plant’s supply network by means of a hose.

SM4-630

Assembly instructions 20

Image 21
Contents Sterling Material Processing SspetParts and Service Department Telephone 800 Edition 02/01 Sterling order confirmation no Technical serviceSSPET5 Table of contents Technical data Parts list Accessories MaintenanceSafety instructions Safety instructionsSSPET5 Explanations and information For your safety SSPET5 SSPET5 For the operating safety of the equipment Assembly instructions Assembly Assembly SM4-630 Mounting the suction pipe MV Electrical connection Installation of the signal line of the SKW optional Installation of the flap switch signal lineSSPET5 Compressed-air supply Functional description General Controller SSE SSPET5 Controller SSP Putting into operation Checking the pipe system Adjusting the suction pipes If the conditions points 3 + 4 are not metIf the conditions points 3 + 4 are met Setting the conveying time Setting the controller SSETurbine is running but no material is being conveyed Conveying capacity is too lowChange-over key Setting the line clear timeSetting the time interval Setting the controller SSPInitial conveying operations Alarm Messages displayed on the controller SSESSPET5 Switching off the unit Alarm Messages displayed on the controller SSPMaintenance SSPET5 Maintenance intervals Servicing the conveyor Removal InstallationChanging the sealing ring of the outlet flap Adjusting the flap switch Replacing carbon brushes at turbine Installation Optional Features Technical dataTechnical data Basic VersionDimension Sheet Parts list SSPET5 Pos Order no Designation Accessories