5.1. Maintenance intervals

Daily:

Check warning signs on equipment for good

 

legibility and completeness

Weekly:

Check the maintanance unit

 

Check operating pressure of the plant’s supply

 

network (5-6 bar (72.52-87.02 PSI) system overpressure)

Monthly:

Check function of the device plug

 

Check the sealings on the filter cartridges

 

(according to the accumulation of dust)

Every 6 months:

Check all electrical and mechanical connections

 

for tight fit

 

Check the settings on the level probes (if present)

 

Check filter contamination, if necessary clean or

 

replace the filter cartridges

Annually:

Replace outlet valve sealing

 

Adjust valve switch

After 1000

 

operating hours:

Replace carbon brushes

F

The given maintenance intervals are average values.

Check whether in your individual case the maintenance in- tervals must be shortened.

SM4-630

Maintenance 37

Image 38
Contents Sspet Sterling Material ProcessingParts and Service Department Technical service Telephone 800 Edition 02/01 Sterling order confirmation noSSPET5 Table of contents Maintenance Technical data Parts list AccessoriesSafety instructions Safety instructionsSSPET5 Explanations and information For your safety SSPET5 SSPET5 For the operating safety of the equipment Assembly instructions Assembly Assembly SM4-630 Mounting the suction pipe MV Electrical connection Installation of the flap switch signal line Installation of the signal line of the SKW optionalSSPET5 Compressed-air supply Functional description General Controller SSE SSPET5 Controller SSP Putting into operation Checking the pipe system If the conditions points 3 + 4 are met Adjusting the suction pipesIf the conditions points 3 + 4 are not met Turbine is running but no material is being conveyed Setting the controller SSESetting the conveying time Conveying capacity is too lowSetting the line clear time Change-over keySetting the controller SSP Setting the time intervalAlarm Messages displayed on the controller SSE Initial conveying operationsSSPET5 Alarm Messages displayed on the controller SSP Switching off the unitMaintenance SSPET5 Maintenance intervals Servicing the conveyor Installation RemovalChanging the sealing ring of the outlet flap Adjusting the flap switch Replacing carbon brushes at turbine Installation Technical data Technical dataOptional Features Basic VersionDimension Sheet Parts list SSPET5 Pos Order no Designation Accessories