Southbend SB1023 manual Assembly, To install the feet

Page 16

Model SB1023

P R E P A R A T I O N

For Machines Mfg. Since 8/09

Assembly

After the machine is placed in the final location, and before the lifting apparatus is removed, you should install the machine feet. Included with your machine are four cushioned feet with built-in adjustment studs (see Figure 7). These feet are easily installed and provide for accurate machine leveling.

To install the feet:

1.Using lifting equipment and wooden blocks, raise and support the machine base so there is approximately 5" between the floor and underside of the base.

2.Remove the jam nuts from the foot studs.

3.Apply any general-purpose automotive grease to the stud threads.

4.Thread the studs into the machine base from the bottom up until the studs emerge from the cabinet floor approximately 2" (see Figure 7).

Foot Stud

Jam Nut

Threaded

Hole

Machine

Foot

Figure 7. Machine feet.

5.Thread the jam nuts onto the protruding studs but do not tighten them at this time.

6.Place the machine onto the floor.

7.Using a precision level on the machine table, adjust the feet studs, so the machine is level from side-to-side and front-to-back.

8.Use a 19mm wrench to tighten the jam nuts inside of the cabinet and lock the feet studs into place.

Note: Over the course of the next six months, periodically verify that the machine is still level, and re-adjust the feet as required.

9.Rotate the top handwheel counterclockwise to raise the headstock slightly. Then remove the wood support block (see Figure 8).

Top

Handwheel

Wood Support

Block

Figure 8. Support block.

10.Using a 14mm wrench, install the two handles into the handwheels (Figure 9).

Figure 9. Headstock height handwheel.

-14-

Image 16
Contents 12 Surface Grinder Updates Customer ServiceScope of Manual Manual FeedbackTable of Contents About This Machine FeaturesCapabilities Identification IdentificationModel SB1023 Machine Specifications12 Surface Grinder Main Specifications Operation Information Basic Machine Safety Understanding Risks of MachineryF E T Y Additional Surface Grinder Safety For Power Connection For AssemblyThings Youll Need Typical preparation process is as followsUnpacking InventoryBefore cleaning, gather the following Cleaning & ProtectingBasic steps for removing rust preventative Location Leveling & Mounting Lifting & MovingLeveling Assembly To install the feetPower Connection SB1023 110V PrewiredTo convert the Model SB1023 to operate on 220V power SB1023 220V OptionInspections Adjustments Test RunInitial Lubrication To test run your machineOperationPERATIONOverview Controls Control panelWheel Selection Abrasive TypeGrit Size GradeRemoving & Installing Grinding Wheels To remove and install a grinding wheelRemove the grinding wheel, as shown in Figure Removing & Installing Wheel & Hub To remove and reinstall the wheel and hubRemove the spindle bolt Figure Wheel Inspection To inspect a wheel for damageWheel Dressing Ring TestTo perform a ring test To dress the grinding wheel Wheel BalancingTo balance the grinding wheel I N T E N a N C E Magnetic Chuck Setup for a Typical Grinding OperationGrinder Operation Using the Surface Grinder Grinding TipsMaintenance Schedule LubricationDaily Bi-weeklyLower column leadscrew Column & Table Gib Adjustment Handwheel Backlash AdjustmentShort-term storage less than year Machine StorageLongng-term-termstoragestorage more than a year Troubleshooting Troubleshooting Lectrical Safety Instructions Wiring Diagram Color KEYSB1023 Wiring Diagram MotorMotor Wired for Motor & Spindle DescriptionColumn See Table Parts List on Column Parts List Table Parts ListStand Machine Labels R R a N T Y #CRJB12368