Southbend SB1023 Maintenance Schedule, Lubrication, Daily, Bi-weekly, To lubricate your machine

Page 32

Model SB1023

M A I N T E N A N C E

For Machines Mfg. Since 8/09

Maintenance

Maintenance Schedule

!

Always disconnect

 

machine from power before

 

performing maintenance or

 

serious personal injury may

 

result.

To keep this machine in the best operating condition, make sure to complete the follow- ing maintenance items within the minimum intervals listed below.

Daily:

Check for and correct loose mounting bolts.

Check for and correct damaged or cracked grinding wheel.

Check for and correct worn or damaged wires.

Clean and protect table.

Vacuum metal shavings from machine.

Correct any other unsafe condition.

Bi-weekly

Remove the table, clean and relubricate the ways, ball bearings, and rack and pinion.

Lubricate the column grease fitting with two pumps of grease.

Lubricate the table cross way grease fitting with two pumps of grease.

Clean and grease all three leadscrews.

Lubrication

If this machine is used in a heavy industrial setting, or in a dirty or damp environment, increase the lubrication intervals.

To lubricate your machine:

1.DISCONNECT MACHINE FROM POWER!

2.Clean the upper column leadscrew section with mineral spirits, dry with a rag, and relubricate with any standard machine or multipurpose grade grease (Figure 37).

Leadscrew

Grease Fitting

Figure 37. Upper column leadscrew and grease fitting.

3.Wipe the column grease fitting clean (see Figure 37) and pump the fitting with two or three pumps of grease. Wipe off any grease that bleeds through the seams.

-30-

Image 32
Contents 12 Surface Grinder Updates Customer ServiceScope of Manual Manual FeedbackTable of Contents Capabilities FeaturesAbout This Machine Identification Identification12 Surface Grinder Machine SpecificationsModel SB1023 Main Specifications Operation Information Basic Machine Safety Understanding Risks of MachineryF E T Y Additional Surface Grinder Safety For Power Connection For AssemblyThings Youll Need Typical preparation process is as followsUnpacking InventoryBasic steps for removing rust preventative Cleaning & ProtectingBefore cleaning, gather the following Location Leveling Lifting & MovingLeveling & Mounting Assembly To install the feetPower Connection SB1023 110V PrewiredTo convert the Model SB1023 to operate on 220V power SB1023 220V OptionInspections Adjustments Test RunInitial Lubrication To test run your machineOperationPERATIONOverview Controls Control panelWheel Selection Abrasive TypeGrit Size GradeRemoving & Installing Grinding Wheels To remove and install a grinding wheelRemove the grinding wheel, as shown in Figure Removing & Installing Wheel & Hub To remove and reinstall the wheel and hubRemove the spindle bolt Figure Wheel Inspection To inspect a wheel for damageTo perform a ring test Ring TestWheel Dressing To balance the grinding wheel Wheel BalancingTo dress the grinding wheel I N T E N a N C E Grinder Operation Setup for a Typical Grinding OperationMagnetic Chuck Using the Surface Grinder Grinding TipsMaintenance Schedule LubricationDaily Bi-weeklyLower column leadscrew Column & Table Gib Adjustment Handwheel Backlash AdjustmentLongng-term-termstoragestorage more than a year Machine StorageShort-term storage less than year Troubleshooting Troubleshooting Lectrical Safety Instructions Wiring Diagram Color KEYSB1023 Wiring Diagram MotorMotor Wired for Motor & Spindle DescriptionColumn See Table Parts List on Column Parts List Table Parts ListStand Machine Labels R R a N T Y #CRJB12368