HP Performance Optimized Data Center (POD) 20cp Environmental considerations, Environmental risks

Page 21

Environmental considerations

Environmental risks

Avoid placing the HP POD 20c directly along a drainage path or in an area prone to flooding.

Verify that the HP POD 20c is properly grounded in accordance with national, regional, and local regulations, ordinances, codes, and the product specifications.

Cold weather

The HP POD 20c requires a site chilled water supply and return, humidifier supply and drain, and condensate drains. Extreme cold weather can cause damage to the supply and drain lines. Evaluate the following for additional cold weather protection:

Regional location of the HP POD 20c

Exposure of the supply and drain lines to extreme cold temperatures

Extreme cold weather can affect crane and lifting operations. When temperatures drop below -12.2°C (10°F), appropriate consideration must be made with respect to shock loading, crane hydraulics, and possible de-rating of the crane.

Areas prone to lightning or power surges

The HP POD 20c structure and internal components are all bonded together. A common Grounding Electrode Conductor Connection point is provided. Proper bonding and grounding of the HP POD 20c minimizes the effects of a lightning strike. A surge protection device is provided on the HP POD 20c input connection to protect the HP POD 20c electrical system from voltage transients. If your site is in an area that is subject to frequent lightning strikes, the HP POD 20c must be protected in accordance with NFPA 70 (NA) and IEC (EMEA and APJ). HP recommends that you contact a certified lightning protection consultant.

Seismic activity

If your site is in an area that has frequent seismic activity, HP recommends that you contact a seismic activity consultant. If your site is in an area that has high vibration level, HP recommends that you contact a vibration isolation consultant. You must specify the method of anchoring the HP POD 20c, if necessary.

Environmental considerations 21

Image 21
Contents Part Number March Edition AbstractPage Contents Appendix a HP site assessment Safety and IEC compliance OverviewAbout this document Feature Specification Site safety and securitySite assessment Site preparationHP POD 20c capacities Electrical power capacities critical IT powerHP POD 20c capacity limitations Overall system capacitiesDimensions and clearances HP POD 20c weightSite requirements Site padSite requirements Future expansions Grounding requirements Utilities Humidifier water supplyFront view shown Requirement Location Specification DrainageChilled water supply Power infrastructure installation Piping materialsParameter Range Site electrical system Electrical power system configurationEnvironmental control system Supported facility connectionsAdditional POD connections Connection portalsEnd view shown Humidifier HP POD 20c access control Fire, safety, and access notifications Fire box Demarcation box Supported facility connections Environmental considerations Areas prone to lightning or power surgesEnvironmental risks Cold weatherCompleting a site assessment Site plan requirements and actionsHP Site Preparation Drawing Package Zoning and permit requirementsSite planning HP POD 20c installationHP POD 20c storage requirements Assembly equipment locations DescriptionAdditional structures Appendix a HP site assessment HP POD 20c site assessment checklistUsed as the basis for the evaluation. The delivery path is Description Yes InitialInformation Customer responsibilities Description InitialInstallation prerequisites HP POD 20c site readiness checklistAppendix B Preparing for delivery Pre-delivery tasksDescription Initial General Water Supply Description InitialChilled Water Supply Description Initial General Description Initial Power Requirements Description InitialSafety and IEC compliance Appendix C Regulatory compliance noticesHP POD 20c regulatory compliance Warranty information Safety and regulatory complianceGlossary Very early smoke detection apparatus Uninterruptible power systemDocumentation feedback Index Site assessment checklist 26 site padIndex
Related manuals
Manual 86 pages 43.14 Kb Manual 22 pages 15.98 Kb Manual 81 pages 57.33 Kb Manual 37 pages 24.34 Kb