Completing a site assessment

HP requires a detailed site assessment prior to planning and preparing the customer site location for the HP POD 20c. Consult with HP to schedule a site assessment.

A standard site assessment visit includes the following tasks:

Selecting an appropriate site for the HP POD 20c

Assessing the proposed site for: o Measurements for clearances

o Infrastructure for the final solution o Access to utilities

o Site pad

o Installation considerations, including locations for delivery trucks, large installation equipment (such as cranes), and storage

o Electrical infrastructure

o Chilled water infrastructure

o Facility network and access control systems

Developing an engagement plan and verifying customer contacts

Discussing future development and growth plans

For a complete site assessment checklist, see "Appendix A: HP site assessment (on page 26)."

HP Site Preparation Drawing Package

After receiving a signed purchase agreement, HP provides detailed engineering drawings. These drawings contain information to assist you and your MEP team to prepare the site for POD installation. If there are areas of special interest, HP can work directly with your MEP team to provide additional assistance.

Zoning and permit requirements

You are responsible for compliance of the overall installation in accordance with all local and national regulations, ordinances, codes, and the product specifications.

Project coordination

Your Project Manager must perform the following tasks:

Coordinate with all trades prior to installation to ensure that trade conflicts are resolved.

Coordinate the installation and integration of all systems.

Site plan requirements and actions 22

Image 22
Contents Abstract Part Number March EditionPage Contents Appendix a HP site assessment Overview Safety and IEC complianceAbout this document Site assessment Site safety and securityFeature Specification Site preparationHP POD 20c capacity limitations Electrical power capacities critical IT powerHP POD 20c capacities Overall system capacitiesSite requirements HP POD 20c weightDimensions and clearances Site padSite requirements Future expansions Grounding requirements Humidifier water supply UtilitiesFront view shown Drainage Requirement Location SpecificationChilled water supply Piping materials Power infrastructure installationParameter Range Electrical power system configuration Site electrical systemAdditional POD connections Supported facility connectionsEnvironmental control system Connection portalsHumidifier End view shownFire, safety, and access notifications HP POD 20c access controlFire box Demarcation box Supported facility connections Environmental risks Areas prone to lightning or power surgesEnvironmental considerations Cold weatherHP Site Preparation Drawing Package Site plan requirements and actionsCompleting a site assessment Zoning and permit requirementsHP POD 20c installation Site planningAssembly equipment locations Description HP POD 20c storage requirementsAdditional structures HP POD 20c site assessment checklist Appendix a HP site assessmentDescription Yes Initial Used as the basis for the evaluation. The delivery path isCustomer responsibilities Description Initial InformationAppendix B Preparing for delivery HP POD 20c site readiness checklistInstallation prerequisites Pre-delivery tasksGeneral Water Supply Description Initial Description InitialChilled Water Supply Description Initial Power Requirements Description Initial General Description InitialAppendix C Regulatory compliance notices Safety and IEC complianceHP POD 20c regulatory compliance Safety and regulatory compliance Warranty informationGlossary Uninterruptible power system Very early smoke detection apparatusDocumentation feedback Site assessment checklist 26 site pad IndexIndex
Related manuals
Manual 86 pages 43.14 Kb Manual 22 pages 15.98 Kb Manual 81 pages 57.33 Kb Manual 37 pages 24.34 Kb