Appendix A: HP site assessment

HP POD 20c site assessment checklist

During a survey of the readiness of a proposed customer site for the HP POD 20c, the site is inspected for the following:

Accessibility of machinery for the transportation and installation of the HP POD 20c

Assessment of the suitability of the site infrastructure for installing the HP POD 20c and for supporting infrastructure preparation and serviceability requirements

HP responsibilities

Item

Description

 

Yes

No

N/A

Initial

 

 

 

 

 

 

 

 

 

1. Engagement plan

Develop an engagement plan with specific requirements

 

 

 

 

 

 

 

relating to the proposed installation site.

 

 

 

 

 

 

2. Site visits

Schedule site visits on mutually acceptable dates, during

 

 

 

 

 

 

 

normal HP business hours.

 

 

 

 

 

 

3. Test equipment

Document any test equipment used in the customer report.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4. Installation site

Review and discuss the proposed installation site with the

 

 

 

 

 

 

review

customer. This initial review includes physical examination of

 

 

 

 

 

 

the proposed installation site and, at the sole discretion of

 

 

 

 

 

 

 

HP, can include physical measurements of the area size and

 

 

 

 

 

 

clearances.

 

 

 

 

 

 

5. Indoor/outdoor

Identify whether the HP POD 20c installation is indoors or

 

 

 

 

 

 

installation

outdoors as this can affect the degree and type of

 

 

 

 

 

 

 

infrastructure required and the mounting needs.

 

 

 

 

 

 

6. Site pad

Inspect the proposed installation site to assess

 

 

 

 

 

 

 

compliance with the HP POD 20c mounting

 

 

 

 

 

 

 

specifications. Ensure that the customer is fully aware of

 

 

 

 

 

 

the following requirements:

 

 

 

 

 

 

 

Proper support capabilities must exist. If the customer

 

 

 

 

 

 

 

intends to edge or point load on the utility and cargo

 

 

 

 

 

 

 

ends, there must be support in the center to prevent

 

 

 

 

 

 

 

deflection.

 

 

 

 

 

 

 

Upon installation, the POD structure must be leveled to

 

 

 

 

 

 

0.5º, which can be checked at that time with a surveyor’s

 

 

 

 

 

 

transit.

 

 

 

 

 

 

 

Shimming is allowed around the perimeter of the POD.

 

 

 

 

 

 

Place shims in increments across the length of the HP

 

 

 

 

 

 

 

POD 20c to ensure that the HP POD 20c is level. If

 

 

 

 

 

 

 

significant shimming is required, shims should be spaced

 

 

 

 

 

 

no less than 1.2 m (4 ft) apart to ensure sufficient load

 

 

 

 

 

 

 

transfer.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7. Materials and

Visually inspect the materials and construction at the

 

 

 

 

 

 

construction

proposed installation site to identify issues that can impact

 

 

 

 

 

 

inspection

the HP POD 20c installation. Verify that the area is adequate

 

 

 

 

 

 

for truck delivery, staging, and crane location.

 

 

 

 

 

 

 

 

Appendix A: HP site assessment 26

Image 26
Contents Abstract Part Number March EditionPage Contents Appendix a HP site assessment About this document Safety and IEC complianceOverview Site assessment Site safety and securityFeature Specification Site preparationHP POD 20c capacity limitations Electrical power capacities critical IT powerHP POD 20c capacities Overall system capacitiesSite requirements HP POD 20c weightDimensions and clearances Site padSite requirements Future expansions Grounding requirements Front view shown UtilitiesHumidifier water supply Chilled water supply Requirement Location SpecificationDrainage Parameter Range Power infrastructure installationPiping materials Electrical power system configuration Site electrical systemAdditional POD connections Supported facility connectionsEnvironmental control system Connection portalsHumidifier End view shownFire box HP POD 20c access controlFire, safety, and access notifications Demarcation box Supported facility connections Environmental risks Areas prone to lightning or power surgesEnvironmental considerations Cold weatherHP Site Preparation Drawing Package Site plan requirements and actionsCompleting a site assessment Zoning and permit requirements HP POD 20c installation Site planningAssembly equipment locations Description HP POD 20c storage requirementsAdditional structures HP POD 20c site assessment checklist Appendix a HP site assessmentDescription Yes Initial Used as the basis for the evaluation. The delivery path isCustomer responsibilities Description Initial InformationAppendix B Preparing for delivery HP POD 20c site readiness checklistInstallation prerequisites Pre-delivery tasksChilled Water Supply Description Initial Description InitialGeneral Water Supply Description Initial Power Requirements Description Initial General Description InitialHP POD 20c regulatory compliance Safety and IEC complianceAppendix C Regulatory compliance notices Safety and regulatory compliance Warranty informationGlossary Uninterruptible power system Very early smoke detection apparatusDocumentation feedback Site assessment checklist 26 site pad IndexIndex
Related manuals
Manual 86 pages 43.14 Kb Manual 22 pages 15.98 Kb Manual 81 pages 57.33 Kb Manual 37 pages 24.34 Kb