HP Performance Optimized Data Center (POD) 20cp manual Description Initial

Page 30

Item

Description

Initial

 

 

 

 

 

10

Verify that the site location has clearances for the HP POD 20c installation, including any

 

 

 

permanent structures, such as fences, walls, vestibules, and buildings.

 

 

11

Verify that all utilities, overhead and underground, are identified to maintain required

 

 

 

clearance.

 

 

12

Verify that there is adequate clearance around the HP POD 20c for door operation,

 

 

 

installation, and maintenance equipment.

 

 

13

Verify that the site location and site pads are marked for any transformer, external

 

 

 

switchboard, generators, and powerhouses.

 

 

14

Verify that the site has provisions for proper grounding and that the site location includes a

 

 

 

grounding electrode system.

 

 

15

Verify that the site location has adequate lighting for the HP POD 20c installation.

 

 

16

Verify that a truck and equipment staging areas are identified.

 

 

17

Verify the location for the fuel tanks for generators, powerhouses, and other equipment, if

 

 

 

applicable.

 

 

18

Verify the locations for cranes off-loading and operation during HP POD 20c installation.

 

 

19

Verify site access and clearances for equipment, including the crane and forklifts. A clear

 

 

 

path to the site must be maintained with clearance for all gates, headers, utility lines, and so

 

 

 

on.

 

 

20

Verify that the locations for storage and trash disposal are identified.

 

 

21

Verify that the safety equipment is planned for and in place in accordance with the

 

 

 

customer’s site safety program.

 

 

22

Verify the site interfaces and locations which connect to the fire alarm, access control system,

 

 

 

and communication system to the HP POD 20c to ensure that the POD can be properly

 

 

 

connected to the site BMS.

 

 

23

Verify that proper disposal methods are used for existing or potentially contaminated and/or

 

 

 

hazardous materials.

 

 

24

Verify the availability of security systems or equipment, including site fences, which are

 

 

 

required after construction.

 

 

25

Verify the availability of temporary facilities associated with the relocation of existing

 

 

 

services and operations.

 

 

26

Verify that all work relating to soil testing, removal, and site remediation is complete.

 

 

27

Verify that a temporary or permanent load bank is available, if applicable.

 

 

28

Verify the location of the EPO system external to the powerhouses, if applicable.

 

 

29

Verify the location of the remote electronic monitoring system.

 

 

30

Verify that tie-downs and other Authority-required facilities for the HP POD 20c and power

 

 

 

containers are complete at least one week prior to arrival of HP-provided equipment.

 

 

General Water Supply

 

 

 

 

 

Item

Description

Initial

 

 

 

 

 

1

Verify that the site drainage is complete, and the HP POD 20c is not in a drainage path or

 

 

 

flood prone area. HP recommends placing the HP POD 20c on a raised site pad to prevent

 

 

 

water from entering the HP POD 20c.

 

 

2

Verify that the humidification water quality meets or exceeds these standards, which are

 

 

 

essentially drinking water standards.

 

 

3

Verify the humidification water supply isolation valve is installed for each POD.

 

 

Chilled Water Supply

 

 

 

 

 

Item

Description

Initial

 

 

 

 

 

1

Verify the chilled water supply and return headers are accessible, are in the appropriate

 

 

 

location, and are 80 cm (3 in) in diameter.

 

 

 

Appendix B: Preparing for delivery 30

Image 30
Contents Abstract Part Number March EditionPage Contents Appendix a HP site assessment Safety and IEC compliance OverviewAbout this document Site assessment Site safety and securityFeature Specification Site preparationHP POD 20c capacity limitations Electrical power capacities critical IT powerHP POD 20c capacities Overall system capacitiesSite requirements HP POD 20c weightDimensions and clearances Site padSite requirements Future expansions Grounding requirements Utilities Humidifier water supplyFront view shown Requirement Location Specification DrainageChilled water supply Power infrastructure installation Piping materialsParameter Range Electrical power system configuration Site electrical systemAdditional POD connections Supported facility connectionsEnvironmental control system Connection portalsHumidifier End view shownHP POD 20c access control Fire, safety, and access notificationsFire box Demarcation box Supported facility connections Environmental risks Areas prone to lightning or power surgesEnvironmental considerations Cold weatherHP Site Preparation Drawing Package Site plan requirements and actionsCompleting a site assessment Zoning and permit requirementsHP POD 20c installation Site planningAssembly equipment locations Description HP POD 20c storage requirementsAdditional structures HP POD 20c site assessment checklist Appendix a HP site assessment Description Yes Initial Used as the basis for the evaluation. The delivery path isCustomer responsibilities Description Initial InformationAppendix B Preparing for delivery HP POD 20c site readiness checklistInstallation prerequisites Pre-delivery tasksDescription Initial General Water Supply Description InitialChilled Water Supply Description Initial Power Requirements Description Initial General Description InitialSafety and IEC compliance Appendix C Regulatory compliance noticesHP POD 20c regulatory compliance Safety and regulatory compliance Warranty informationGlossary Uninterruptible power system Very early smoke detection apparatusDocumentation feedback Site assessment checklist 26 site pad IndexIndex
Related manuals
Manual 86 pages 43.14 Kb Manual 22 pages 15.98 Kb Manual 81 pages 57.33 Kb Manual 37 pages 24.34 Kb