Rinnai RL75I, RL94I Flushing the Heat Exchanger Error Code LC or, Circulating Pump

Page 15

Flushing the Heat Exchanger (Error Code: LC or 00)

An “LC” or “00” error code indicates the unit is beginning to lime up and must be flushed. Failure to flush the appliance will cause damage to the heat exchanger. Damage caused by lime build-up is not covered by the unit’s warranty. After flushing, reset the LC fault code by turning off the power to the unit and turning the power back on.

1.Disconnect electrical power to the water heater.

2.Close the shutoff valves on both the hot water and cold water lines (V3 and V4).

3.Connect pump outlet hose (H1) to the cold water line at service valve (V2).

4.Connect drain hose (H3) to service valve (V1).

5.Pour 4 gallons of undiluted virgin, food grade, white vinegar into pail.

6.Place the drain hose (H3) and the hose (H2) to the pump inlet into the cleaning solution.

7.Open both service valves (V1 and V2) on the hot water and cold water lines.

8.Operate the pump and allow the cleaning solution to circulate through the water heater for 1 hour at a rate of 4 gallons per minute (15.1 liters per minute).

9.Turn off the pump.

10.Rinse the cleaning solution from the water heater as follows:

a.Remove the free end of the drain hose (H3) from the pail.

b.Close service valve, (V2), and open shutoff valve, (V4). Do not open shutoff valve, (V3).

c.Allow water to flow through the water heater for 5 minutes

d.Close service valve, (V1), and open shutoff valve, (V3).

11.Disconnect all hoses.

12.With (V4) closed, remove the in-line filter at the cold water inlet and clean out any residue. Place filter back into unit and open (V4).

13.Restore electrical power to the water heater.

KEY

3/4" Ball Valve

Pressure Regulator

 

3/4" Union

Circulating Pump

Check Valve

Boiler Drain Valve

Pressure Relief Valve

S Solenoid Valve

Rinnai

Water Heater

In-line

Filter

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

V1

 

 

 

 

 

 

 

 

V2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

CLEAN THERMISTORS

Remove and clean thermistors with a soft cloth or sponge after removing O-rings.

Cleaning solution is 4 gallons of undiluted virgin, food grade, white vinegar.

H3

V3

V4

 

 

 

 

 

Hot

Cold

Gas

 

Supply

 

Water

 

Water

 

 

Line

 

 

Line

 

 

 

 

H2

H1

Circulating Pump

VB Series Indoor LS Manual

15

Image 15
Contents REU-VB2528FFUD-US Table of Contents RL75i RL94i R98LSi SpecificationsDescription of Operation Consumer Safety InformationSafety Definitions Safety Behaviors and Practices Safety FeaturesMC-91-1US & MCC-91-1US Temperature ControllerMC-91 MCC-91 MC-100 BC-100 MC-502 Description Features Available on Temperature ControllersFeatures Operating InstructionsHow to Set the Temperature Temperature Controller SettingsModel Temperature Settings Available ºF MCC-91 Temperature Controller Temperature Options Without a Temperature ControllerSetting the Sound Volume Voice Prompt Re-setting the Maximum Temperature RL75 and RL94 onlyUsing the Water Smart / Bath Fill Function Setting the Water VolumeOverview Models MC-91 and MCC-91 Setting Controller to MuteSetting the Clock Filling the TubMaintenance Code Fault Remedy Error CodesCode Trouble Shooting for Common Issues Accessing Operating InformationWater Quality Circulating Pump Flushing the Heat Exchanger Error Code LC orGeneral Instructions Installation InstructionsAttachment of the Water Heater Clearances from ApplianceElectrical Connection Gas PipingGeneral Instructions Pipe Sizing Procedure Example Water Piping Isolation Valves Installation InstructionsPressure Relief Valve Installation Instructions Pressure Relief Valve MaintenancePiping Requirements Pressure Relief Valve RequirementsFreeze Protection When the water heater or external piping has frozen Freeze ProtectionManual draining of the water heater KEY Freeze Protection PipingRinnai Water Heater Recommended Piping for Basic InstallationFor this application Recommended Piping for Circulation SystemsVenting Instructions Intake / Exhaust GuidelinesCondensate Maximum Vent Length Manufacturer Product Parts Vent ProductsFlue Terminal Clearances ANS Z21.10.3, CSA Description Canadian Installations US InstallationsInside Corner Additional Clearances Vent TerminalFlue Installation Concentric Venting RL75i, RL94i Venting Clearances to Combustibles Flue Installation R98LSi, R98LSi-ASMEAir Intake Assembly Exhaust Pipe AssemblyVertical Terminations Horizontal with Concentric TerminationGuidelines Connecting Multiple Water HeatersHigh Altitude Installations Number Connected Accessories Necessary Water HeatersCanada only Cable Lengths and Size Temperature Controller InstallationConfigurations LocationOutline of Remote Mounting the ControllerOperating Instructions For Your Safety Read Before OperatingTechnical Data Pressure Drop CurveOutlet Flow Data Pumps Temperature SettingReplacement Space HeatingRL75i, RL94i R98LSi, R98LSi-ASME DimensionsLadder Diagram for RL75i and RL94i HOT Ladder Diagram for R98LSi and R98LSi-ASMEWarranty Information Limited WarrantyConsumer Support What will Rinnai do? Important In the State of Massachusetts 248 CMR 4.00 State RegulationsInstructions dutilisation Instructions d’installationTemp. d’eau Instructions dutilisationPlages de température avec un contrôleur de température Options de température sans contrôleur à distanceModel Plages de température disponible ºF Nettoyage EntretienInstructions générales Fixation du chauffe-eau Écartements par rapport à lappareilInstallation à altitude élevée Tuyauterie de gazInstructions générales Valve à Bille / Valve de dégagement de pression RL75i, RL94i Tuyauterie deauSoupape de sûreté Qualité de leauLégende Tuyauterie recommandée pour installation de baseInstructions de ventilation Consignes pour aspiration/évacuationCondensat 12.5 m 10.7 m Longueur maximum de ventilationProduits de ventilation Constructeur Produit PiècesHorizontale Nest PAS Permise Espacements pour terminaison de cheminée ANS Z21.10.3, CSAInstallation de conduit de cheminée RL75i, RL94i Terminaisons horizontales Installation de conduit de cheminée R98LSi, R98LSi-ASMEEnsemble de prise dair Montage du tuyau dévacuationTerminaisons verticales Terminaison horizontale concentriqueVanneMa ualmanuelleValve Instructions dutilisationPhase Diagramme en escalier RL75i, RL94iPhase TRE NEU RAL Diagramme en escalier R98LSi, R98LSiASMECombien de temps dure la couverture ? Support à la clientèleInformations sur la garantie Quest-ce qui est couvert ?Que fait Rinnai pour exercer la garantie ? VB Series Indoor LS Manual VB Series Indoor LS Manual VB Series Indoor LS Manual VB2528FFU VB2735FFU VA3237FFU