Electrical Connection

The water heater requires 120 VAC, 60 Hz power from a properly grounded circuit.

If using the 6 foot long power cord, plug it into a standard 3 prong 120 VAC, 60 Hz properly grounded wall outlet. The wiring diagram is located on the Technical Sheet attached to the inside of the front cover.

The water heater must be electrically grounded in accordance with local codes, or in the absence of local codes with the National Electrical Code, ANSI/NFPA 70 and/or the CSA C22.1, Canadian Electrical Code.

Error Indication or Air Handler Control Switch (RL75i, and RL94i only)

When using the Rinnai water heater with an Error Indication Switch, switch No. 4 in the bank of 8 switches should be in the off position. This is the default position.

To connect the water heater to the Rinnai Air Handler, the Control Switch is necessary to function as the electrical connection. When the Control Switch is functioning as the electrical connection between the water heater and air handler, switch No. 4 in the bank of 8 switches should be in the on position.

The Error Indication Switch and the Rinnai Air Handler Control Switch are optional products available from Rinnai. Installation instructions are included with these products.

Gas Piping

General Instructions

A manual gas control valve must be placed in the gas supply line to the Rinnai water heater. A union can be used on the connection above the shut off valve for the future servicing or disconnection of the unit.

Check the type of gas and the gas inlet pressure before connecting the Rinnai water heater. If the Rinnai water heater is not of the gas type that the building is supplied with, DO NOT connect the water heater. Contact the dealer for the proper unit to match the gas type.

Check the gas supply pressure immediately upstream at a location provided by the gas company. Supplied gas pressure must be within the limits shown in the Specifications section.

Before placing the appliance in operation all joints including the heater must be checked for gas tightness by means of leak detector solution, soap and water, or an equivalent nonflammable solution, as applicable. (Since some leak test solutions,

including soap and water, may cause corrosion or stress cracking, the piping shall be rinsed with water after testing, unless it has been determined that the leak test solution is non-corrosive.)

Always use approved connectors to connect the unit to the gas line. Always purge the gas line of any debris before connection to the water heater.

The gas supply line shall be gas tight, sized, and so installed as to provide a supply of gas sufficient to meet the maximum demand of the heater and all other gas consuming appliances at the location without loss of pressure.

Any compound used on the threaded joint of the gas piping shall be a type which resists the action of liquefied petroleum gas (propane / LPG).

Refer to an approved pipe sizing chart if in doubt about the size of the gas line.

18

VB Series Indoor LS Manual

Image 18
Contents REU-VB2528FFUD-US Table of Contents Specifications RL75i RL94i R98LSiSafety Behaviors and Practices Safety Features Consumer Safety InformationSafety Definitions Description of OperationTemperature Controller MC-91-1US & MCC-91-1USOperating Instructions Features Available on Temperature ControllersFeatures MC-91 MCC-91 MC-100 BC-100 MC-502 DescriptionHow to Set the Temperature Temperature Controller SettingsModel Temperature Settings Available ºF Re-setting the Maximum Temperature RL75 and RL94 only Temperature Options Without a Temperature ControllerSetting the Sound Volume Voice Prompt MCC-91 Temperature ControllerUsing the Water Smart / Bath Fill Function Setting the Water VolumeOverview Filling the Tub Setting Controller to MuteSetting the Clock Models MC-91 and MCC-91Maintenance Error Codes Code Fault RemedyCode Trouble Shooting for Common Issues Accessing Operating InformationWater Quality Flushing the Heat Exchanger Error Code LC or Circulating PumpInstallation Instructions General InstructionsClearances from Appliance Attachment of the Water HeaterElectrical Connection Gas PipingGeneral Instructions Pipe Sizing Procedure Example Pressure Relief Valve Maintenance Isolation Valves Installation InstructionsPressure Relief Valve Installation Instructions Water PipingPiping Requirements Pressure Relief Valve RequirementsFreeze Protection When the water heater or external piping has frozen Freeze ProtectionManual draining of the water heater Freeze Protection Piping KEYRecommended Piping for Basic Installation Rinnai Water HeaterRecommended Piping for Circulation Systems For this applicationVenting Instructions Intake / Exhaust GuidelinesCondensate Maximum Vent Length Vent Products Manufacturer Product PartsDescription Canadian Installations US Installations Flue Terminal Clearances ANS Z21.10.3, CSAAdditional Clearances Vent Terminal Inside CornerFlue Installation Concentric Venting RL75i, RL94i Exhaust Pipe Assembly Flue Installation R98LSi, R98LSi-ASMEAir Intake Assembly Venting Clearances to CombustiblesHorizontal with Concentric Termination Vertical TerminationsNumber Connected Accessories Necessary Water Heaters Connecting Multiple Water HeatersHigh Altitude Installations GuidelinesCanada only Location Temperature Controller InstallationConfigurations Cable Lengths and SizeMounting the Controller Outline of RemoteFor Your Safety Read Before Operating Operating InstructionsTechnical Data Pressure Drop CurveOutlet Flow Data Space Heating Temperature SettingReplacement PumpsDimensions RL75i, RL94i R98LSi, R98LSi-ASMELadder Diagram for RL75i and RL94i Ladder Diagram for R98LSi and R98LSi-ASME HOTWarranty Information Limited WarrantyConsumer Support What will Rinnai do? State Regulations Important In the State of Massachusetts 248 CMR 4.00Instructions d’installation Instructions dutilisationInstructions dutilisation Temp. d’eauPlages de température avec un contrôleur de température Options de température sans contrôleur à distanceModel Plages de température disponible ºF Entretien NettoyageInstructions générales Écartements par rapport à lappareil Fixation du chauffe-eauInstallation à altitude élevée Tuyauterie de gazInstructions générales Tuyauterie deau Valve à Bille / Valve de dégagement de pression RL75i, RL94iQualité de leau Soupape de sûretéTuyauterie recommandée pour installation de base LégendeInstructions de ventilation Consignes pour aspiration/évacuationCondensat Longueur maximum de ventilation 12.5 m 10.7 mProduits de ventilation Constructeur Produit PiècesHorizontale Espacements pour terminaison de cheminée ANS Z21.10.3, CSA Nest PAS PermiseInstallation de conduit de cheminée RL75i, RL94i Montage du tuyau dévacuation Installation de conduit de cheminée R98LSi, R98LSi-ASMEEnsemble de prise dair Terminaisons horizontalesTerminaison horizontale concentrique Terminaisons verticalesInstructions dutilisation VanneMa ualmanuelleValveDiagramme en escalier RL75i, RL94i PhaseDiagramme en escalier R98LSi, R98LSiASME Phase TRE NEU RALQuest-ce qui est couvert ? Support à la clientèleInformations sur la garantie Combien de temps dure la couverture ?Que fait Rinnai pour exercer la garantie ? VB Series Indoor LS Manual VB Series Indoor LS Manual VB Series Indoor LS Manual VB2528FFU VB2735FFU VA3237FFU