Heat & Glo LifeStyle 550TRSI-AUF Assemble Vent Sections SLP Pipe Only, Assemble Slip Sections

Page 46

B. Assemble Vent Sections (SLP Pipe Only)

To attach the first vent component to the starting collars of the appliance:

Lock the vent components into place by sliding the pipe section onto the collar.

Align the seam of the pipe and seam of collar to allow engagement. Rotate the vent component to lock into place. Use this procedure for all vent components. See Figure 10.5.

Slide the gasket over the first vent section and place it flush to the appliance. This will prevent cold air infiltra- tion. High temperature caulk may be used to hold the part in place.

Continue adding vent components, locking each succeeding component into place.

Ensure that each succeeding vent component is securely fitted and locked into the preceding component.

Commercial, Multi-family (Multi-level exceeding two sto- ries), or High-Rise Applications

For Installation into a commercial, multi-family (multi-level exceeding two stories) or high-rise applications: All outer pipe joints must be sealed with high temperature silicone, including the slip section that connects directly to the hori- zontal termination cap.

Apply a bead of silicone sealant inside the female outer pipe joint prior to joining sections. See Figure 10.1.

Only outer pipes need to be sealed. All unit collar, pipe, slip section, elbow and cap outer flues shall be sealed in this manner, unless otherwise stated.

WARNING! Risk of Fire or Explosion! DO NOT break silicone seals on slip sections. Use care when remov- ing termination cap from slip pipe. If slip section seals are broken during removal of the termination cap, vent may leak.

Note: Align seams to engage pipe, then rotate counterclockwise to lock

Figure 10.5 Adding Venting Components

C. Assemble Slip Sections

Slide the inner flue of the slip section into the inner flue of the pipe section and the outer flue of the slip section over the outer flue of the pipe section. See Figure 10.6.

Slide together to the desired length.

Pilot hole

Figure 10.6 Slip Section Pilot Holes

Maintain a 1-1/2 in. (38 mm) overlap between the slip section and the pipe section.

Secure the pipe and slip section with two screws no longer than 1/2 in. (13 mm), using the pilot holes in the slip section. See Figure 10.7.

Figure 10.7 Screws into Slip Section

Continue adding pipe as necessary following instructions in “Assembling Pipe Sections.”

NOTICE: If slip section is too long, the inner and outer flues of the slip section can be cut to the desired length.

NOTICE: When installing a vent system with an HRC termination cap, all pipe system joints shall be sealed using a high temperature silicone sealant.

Apply a bead of silicone sealant inside the female outer pipe joint prior to joining sections.

Only outer pipes are sealed, sealing the inner flue is not required.

All unit collar, pipe, slip section, elbow and cap outer flues shall be sealed.

46

Heat & Glo • 550TRSI-AUF, 550TRSILP-AUF2079-980 Rev. N • 5/12

 

Image 46
Contents What to do if you smell gas Models 550TRSI-AUF 550TRSILP-AUFRef No GSCS20163 Sans 15392008 AS45532008 Hot glass will cause burnsModels 550TRSI-AUF, 550TRSILP-AUF Congratulations Homeowner Reference InformationSans Compliance Novida Testing ServiceSans Table of Contents User GuideGas Information Appliance SetupTroubleshooting Electrical InformationAustralian Warranty Information Limited Lifetime WarrantyOther Rights This warranty is void if PerthListing and Code Approvals Operating Instructions User Guide Gas Fireplace SafetyYour Fireplace Fan Kit Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Clear SpaceLighting Instructions IPI Final inspection byNine Hour Safety Shutdown Feature Control Module OperationFrequently Asked Questions After Fireplace is LitMaintenance and Service Logs Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection FireboxGetting Started Typical Appliance SystemInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Any such action may cause a fire hazardFraming and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesMinimum Framing Dimensions Combustible Mantels Mantel and Wall ProjectionsCombustible Mantel Legs or Wall Projections Termination Locations Vent Termination Minimum ClearancesMIN. Clearance in. mm ClearanceVent Information and Diagrams Top Vent Horizontal Termination V1 Minimum H1 MaximumTop Vent Horizontal Termination Two Elbows Minimum + H 2 MaximumThree Elbows Min MaxTop Vent Vertical Termination Straight Up Vertical Flue SystemFlue System Approvals And Installations Flue Termination ApprovalsTop Vent Vertical Termination Two Elbows H1 Maximum V1 + V2 MinTop Vent Vertical Termination Three Elbows H1 + H2 V1 + V2 Minimum H1 + H2 MaximumOne 45º Elbow Rear Vent Horizontal Termination No ElbowH1 Minimum H1 Maximum Rear Vent Horizontal Termination Two Elbows H3H2Minimum Maximum Rear Vent Vertical Termination One Elbow Two ElbowsV1 Minimum H1 + H2 Maximum Maximum Minimum + H 2 Maximum Rear Vent Vertical Termination Three ElbowsMinimum + H 2 + H Maximum Combustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration Framing Non-Combustible Wall PenetrationInstall the Ceiling Firestop Pipe DVP SLPFlat Ceiling Installation Install Attic Insulation ShieldInstalling the Optional Heat-Zone-240V Kit Vaulted Ceiling InstallationAppliance Preparation Top VentRear Vent Cut the metal retaining band and fold the sides outInstalling the Non-combustible Board Securing and Leveling the ApplianceAdjustments And Replacement Parts Components Removal For ServiceParts Replacement Install Trim and/or SurroundAssemble Vent Sections DVP Pipe Only Installing Vent Pipe DVP and SLP PipeAttach Vent to the Firebox Assembly Assemble Pipe SectionsAssemble Vent Sections SLP Pipe Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Support Brackets Install FirestopsFor Horizontal Terminations using the SLP-TRAP2 or DVP-TRAP2 Flue TerminationInstall Metal Roof Flashing Heat Shield Requirements for Horizontal TerminationAssemble and Install Storm Collar Install Vertical Termination CapGas Information Gas ConnectionGAS Access Optional Accessories Requirements Wiring RequirementsIntelliFire Plus Ignition System Wiring Optional Remote Control Receiver LocationBlower Fireplace Specific Information Kit ContentsInstallation Precautions IntroductionChanging Temperature Scale Installation of Remote Control HousingFan Installation AUX300CE Module InstallationProgramming the RC300AU to the Control Module Display Screen Idle When Remote is in on ModeStandby mode Function ButtonsAdjusting Flame Height About on ModeAbout OFF Mode Adjusting Fan SpeedSetting the Child Lock Adjusting ThermostatAdjusting Timer Power OutageFrequently Asked Questions/Troubleshooting Symptom Possible Cause Corrective ActionFacing Material Finishing816 940 Clean the Appliance Appliance SetupRemove Fixed Glass Assembly AccessoriesLog Placement Instructions 3 4 5 6 7Heat & Glo 550TRSI-AUF, 550TRSILP-AUF 2079-980 Rev. N 5/12 Heat & Glo 550TRSI-AUF, 550TRSILP-AUF 2079-980 Rev. N 5/12 Symptom Possible Cause Corrective Action TroubleshootingIntelliFire Plus Ignition System Troubleshooting Reference Materials Appliance Dimension DiagramLocation Inches Millimeters Maintenance Tasks Inspect Maintenance TasksVent Components Diagrams DVP-AS2Effective Length Mm Heat Shield 15-1/8 384 mmHorizontal Termination Cap DVP-HRC-SS DVP-HRC-ZC-SS Elbow 165 mm165 mm 222 mm 235 mm 152 mm 168 mm 251 mmCathedral Ceiling Heat Shield 15-1/8 384 mmEffective HorizontalService Parts Log Set Assembly#19 Valve Assembly Beginning Manufacturing Date July Ending Manufacturing DateService Parts List Conversion KitsContact Information