11 Gas Information

A. Gas Pressure Requirements

WARNING! Risk of Explosion! An in-line regulator MUST be installed if the gas pressure exceeds 3.7 kPa. Failure to install a regulator could damage valve.

Pressure requirements for 550TRSI-AUF and 550TRSILP- AUF fireplaces are shown in the table below.

Two taps are provided on the right hand side of the gas control for a test gauge connection to measure the inlet and outlet pressures.

The fireplace and its individual shut-off valve must be dis- connected from the gas supply piping system during any pressure testing of the system at test pressures in excess of 6 kPa.

If the fireplace must be isolated from the gas supply pip- ing system by closing an individual shut-off valve, it must be of the handle-less type.

WARNING

Fire Risk

Explosion Risk

High pressure will damage valve.

Disconnect gas supply piping BEFORE pressure testing gas line at test pressures above 6 kPa.

Close the manual shutoff valve BEFORE pressure testing gas line at test pressures equal to or less than 6 kPa.

B.Gas Connection

Note: Have the gas supply line installed in accordance with local building codes by a qualified installer approved and/or licensed as required by the locality.

Note: Before the first firing of the appliance, the gas supply line should be purged of any trapped air.

Note: Consult local building regulations to properly size the gas supply line leading to the (Rp 1/2 in.) hook-up at the unit.

Incoming gas line should be piped into the valve compart- ment and connected to the ISO 7-Rp 1/2 (BSP Rp 1/2) threaded gas inlet connection on the manual shutoff valve.

IMPORTANT NOTICE: (Items 1, 2 and 3 applies to ALL Heat & Glo gas appliances)

1.1/2 in. GAS LINE: Run through cavity 70 mm above finished hearth level, NOT RIGID, NOT CLIPPED, with minimum 500 mm into cavity and 120 mm back from plaster face.

2.PVC (COMPOSITE) GASLINE must terminate minimum 500 mm short of gas heater. Copper pipe MUST be the final connection to the gas heater.

3.ISOLATING SWITCH: Location within 1 metre of fireplace, subject to mantelpiece etc. Check to ensure it remains clear of any mantelpiece instal- lation.

Leak test all gas line points and the gas control valve prior to and after starting the gas appliance.

WARNING

CHECK FOR GAS LEAKS

Explosion Risk

Fire Risk

Asphyxiation Risk

Check all fittings and connections.

Do not use open flame.

After the gas line installation is complete, all

connections must be tightened and checked for leaks with a commercially-available, non- corrosive leak check solution. Be sure to rinse off all leak check solution following testing.

Fittings and connections may have loosened during shipping and handling.

 

Natural Gas

Propane

Inlet Gas Pressure

1.13

- 3.40 kPa

2.75 - 3.40 kPa

Outlet (Manifold) Gas Pressure

.80

- .95 kPa

2.36 - 2.61 kPa

Maximum Gas Consumption

28 MJ/h

26 MJ/h

Burner Injector

DMS 40 (2.49 mm)

.057 DMS (1.45 mm)

Pilot Injector

 

.0121

0.0181

An in-line regulator MUST be installed if the gas pressure exceeds 3.40 kPa. Failure to install a regulator could damage valve.

52

Heat & Glo • 550TRSI-AUF, 550TRSILP-AUF2079-980 Rev. N • 5/12

 

Image 52
Contents Models 550TRSI-AUF 550TRSILP-AUF Ref No GSCS20163 Sans 15392008 AS45532008What to do if you smell gas Hot glass will cause burnsModels 550TRSI-AUF, 550TRSILP-AUF Congratulations Homeowner Reference InformationSans Compliance Novida Testing ServiceSans Table of Contents User GuideAppliance Setup TroubleshootingGas Information Electrical InformationAustralian Warranty Information Limited Lifetime WarrantyOther Rights This warranty is void if PerthListing and Code Approvals Operating Instructions User Guide Gas Fireplace SafetyYour Fireplace Fixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesFan Kit Clear SpaceLighting Instructions IPI Final inspection byNine Hour Safety Shutdown Feature Control Module OperationFrequently Asked Questions After Fireplace is LitMaintenance and Service Maintenance Tasks-Qualified Service Technician Gasket Seal and Glass Assembly InspectionLogs FireboxGetting Started Typical Appliance SystemDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Any such action may cause a fire hazardFraming and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesMinimum Framing Dimensions Combustible Mantels Mantel and Wall ProjectionsCombustible Mantel Legs or Wall Projections Termination Locations Vent Termination Minimum ClearancesMIN. Clearance in. mm ClearanceVent Information and Diagrams Top Vent Horizontal Termination V1 Minimum H1 MaximumTop Vent Horizontal Termination Two Elbows Minimum + H 2 MaximumThree Elbows Min MaxTop Vent Vertical Termination Straight Up Vertical Flue SystemFlue System Approvals And Installations Flue Termination ApprovalsTop Vent Vertical Termination Two Elbows H1 Maximum V1 + V2 MinTop Vent Vertical Termination Three Elbows H1 + H2 V1 + V2 Minimum H1 + H2 MaximumOne 45º Elbow Rear Vent Horizontal Termination No ElbowH1 Minimum H1 Maximum Rear Vent Horizontal Termination Two Elbows H3H2Minimum Maximum Rear Vent Vertical Termination One Elbow Two ElbowsV1 Minimum H1 + H2 Maximum Maximum Minimum + H 2 Maximum Rear Vent Vertical Termination Three ElbowsMinimum + H 2 + H Maximum Vent Clearances and Framing Pipe Clearances to Combustibles Wall Penetration FramingCombustible Wall Penetration Non-Combustible Wall PenetrationInstall the Ceiling Firestop Pipe DVP SLPInstall Attic Insulation Shield Installing the Optional Heat-Zone-240V KitFlat Ceiling Installation Vaulted Ceiling InstallationAppliance Preparation Top VentRear Vent Cut the metal retaining band and fold the sides outInstalling the Non-combustible Board Securing and Leveling the ApplianceComponents Removal For Service Parts ReplacementAdjustments And Replacement Parts Install Trim and/or SurroundInstalling Vent Pipe DVP and SLP Pipe Attach Vent to the Firebox AssemblyAssemble Vent Sections DVP Pipe Only Assemble Pipe SectionsAssemble Vent Sections SLP Pipe Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Support Brackets Install FirestopsFor Horizontal Terminations using the SLP-TRAP2 or DVP-TRAP2 Flue TerminationInstall Metal Roof Flashing Heat Shield Requirements for Horizontal TerminationAssemble and Install Storm Collar Install Vertical Termination CapGas Information Gas ConnectionGAS Access Wiring Requirements IntelliFire Plus Ignition System WiringOptional Accessories Requirements Optional Remote Control Receiver LocationBlower Kit Contents Installation PrecautionsFireplace Specific Information IntroductionChanging Temperature Scale Installation of Remote Control HousingFan Installation AUX300CE Module InstallationProgramming the RC300AU to the Control Module Idle When Remote is in on Mode Standby modeDisplay Screen Function ButtonsAbout on Mode About OFF ModeAdjusting Flame Height Adjusting Fan SpeedAdjusting Thermostat Adjusting TimerSetting the Child Lock Power OutageFrequently Asked Questions/Troubleshooting Symptom Possible Cause Corrective ActionFacing Material Finishing816 940 Appliance Setup Remove Fixed Glass AssemblyClean the Appliance AccessoriesLog Placement Instructions 3 4 5 6 7Heat & Glo 550TRSI-AUF, 550TRSILP-AUF 2079-980 Rev. N 5/12 Heat & Glo 550TRSI-AUF, 550TRSILP-AUF 2079-980 Rev. N 5/12 Symptom Possible Cause Corrective Action TroubleshootingIntelliFire Plus Ignition System Troubleshooting Reference Materials Appliance Dimension DiagramLocation Inches Millimeters Maintenance Tasks Inspect Maintenance TasksVent Components Diagrams DVP-AS2Effective Length Mm Heat Shield 15-1/8 384 mmHorizontal Termination Cap DVP-HRC-SS DVP-HRC-ZC-SS 165 mm 165 mm 222 mm 235 mm 152 mm 168 mmElbow 251 mmHeat Shield 15-1/8 384 mm EffectiveCathedral Ceiling HorizontalService Parts Log Set Assembly#19 Valve Assembly Beginning Manufacturing Date July Ending Manufacturing DateService Parts List Conversion KitsContact Information