Vermont Casting DTV38s2 Zero clearance sleeve is only required for combustible walls

Page 20

Chateau™ Direct Vent Gas Fireplace

Vent Opening for Combustible Wall

16¹⁄

(413mm)

16¹⁄

 

 

 

 

 

 

Framing

 

 

 

 

Detail

(413mm)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Fireplace Hearth

Vent Opening for Noncombustible Wall

11¹⁄

(286mm)

VO584-100

Fig. 19 Locate vent opening on wall.

STEP 2

Measure wall thickness and cut zero clearance sleeve parts to proper length (MAXIMUM 12”/305 mm). As- semble sleeve using #8 sheet metal screws (supplied). (Fig. 20) Install firestop assembly. (Fig. 35)

Zero clearance sleeve is only required for combustible walls.

Adjustable Zero

 

Clearance Sleeve

Max. Length

 

12” (305mm)

 

#8 Screws (2)

#8 Screws (2)

 

 

ZCS101a

Fig. 20 Adjustable zero clearance sleeve.

 

STEP 3

Slide the zero clearance sleeve through the wall and install the firestop on the inside surface of the wall. Secure with four (4) #8 sheet metal screws.

STEP 4

Place fireplace into position. (Fig. 21) Measure the ver- tical height (X) required from the base of the flue collars to the center of the wall opening. NOTE: If using the SK8DVSK Kit, the vertical section of pipe is telescopic and could provide adjustment from 24” up to 40” (610 to 1016 mm).

Firestop

Zero Clear-

ance Sleeve

X

FP1456

Fig. 21 Vertical height requirement.

STEP 5

Tape the inner and outer flue collars of the fireplace using UL approved metal adhesive tape to ensure the joints are sealed. Attach an appropriate length of vent pipe to the fireplace. Follow with the installation of the inner and outer elbow, tape elbow joints and secure joints as described on Page 17.

STEP 6

Measure the horizontal length requirement including a 2” (51 mm) overlap, ie from the elbow to the outside wall face plus 2” (51 mm) (or the distance required if installing a second 90° elbow). (Fig. 22)

Always install horizontal venting on a level plane.

STEP 7

Use appropriate length of pipe sections and install the horizontal vent sections. You may need to cut 1’ wall section to size to be flush with the outside wall. The sections which go through the wall are packaged with the starter kit, and can be cut to suit if necessary. (Fig. 23)

Sealing firestop gaps with high temperature sealant will restrict cold air being drawn in around fire- place.

STEP 8

Guide the vent terminations 8” and 11” collars into their respective vent pipes. Double check that the vent pipes overlap the collars by 2” (51 mm). Secure the termina- tion to the wall with screws provided and caulk around the wall plate to weatherproof. (Fig. 24) As an alterna- tive to screwing the termination directly to the wall you may also use expanding plugs or an approved exterior construction adhesive.

20

20011957

Image 20
Contents INSTALLER/CONSUMER Safety Information What to do if YOU Smell GASTable of Contents Installation & Operating Instructions Certified ToAnsi Z21.50b-2005 / CSA 2.22b-2005 Vented Gas Fireplace Please Review the Following CarefullyGas Equipment Venting System not Provided Requirements for the Commonwealth of MassachusettsClear of ALL Obstructions Locating Your Fireplace Standard FramingClearance to Combustibles MantelsFinal Finishing HearthFraming and Finishing Gas Line Installation Gas SpecificationsGas Inlet and Manifold Pressures High ElevationsControl System Installation Control SystemSpecial Feature for Cold Climates Inside view of wireless wall switchHand-Held Remote Control Transmitter Operating Instructions Key SettingsIntroduction LCD Liquid Crystal DisplayManual Function Thermostat FunctionSetting LOCK-OUT CP Continuous Pilot FeatureCP Childproof Feature Thermostatic Updating Feature Operational NotesGeneral Venting Location of Vent TerminationCanadian Installations1 US Installations2 General Venting Information Termination LocationGeneral Information Assembling Vent Pipes SK8 Venting Pipes Canadian InstallationsUSA Installations Sidewall Applications Horizontal TerminationVertical Termination Sidewall Installation StepAlways install horizontal venting on a level plane Zero clearance sleeve is only required for combustible wallsSidewall Installation with Stationary Glass Facing Outside Horizontal length requirementInstallation Procedure Installing the 38S2VDK DoorFlue Restrictor Plate Installation Restrictor Plate InstallationFlue Restrictor Plate Guide Typical ApplicationsFlue restrictor plate use in straight up installation Vertical Through-the-Roof Installation + 2 + 3 + 4 =Min Chimney Components Component Description Model NumberGlass Frame Assembly Removal Glass CleaningCeramic Refractory Installation Clean the glass after the first two weeks of operationLog, Lava Rock and Ember Placement DVT38Sw log identificationLog Pilot Plumbing F50 Overlay is very fragile Log Right Flame Characteristics Trim Installation Turning Off the Gas to the Appliance Lighting & Operating InstructionsLighting Instructions Operation TroubleshootingAmerican Flame Gas Control System Troubleshooting American Flame Gas Control System American Flame Gas Control System Error Codes What to CheckFuel Conversion Instructions Conversion PrecautionsConversion Procedure Remove pilot orifice Pilot Flame Adjustment DVT38S2 Injector Orifice Size MatrixValve Minimum Rate Screw Conversion to LPBurner and Burner Compartment MaintenanceCleaning the Control System DVT38S2 Units GFYW5Q0 DVT38S2 DVT38S2Fuel Conversion Kits Wall Mountable Wireless Remote Transmitter AccessoriesBack-up Battery Kit Limited Lifetime Warranty Product Covered by this WarrantyEfficiency Ratings Model EnerGuide Ratings Fireplace Efficiency %