Vermont Casting DTV38s2 installation instructions Min

Page 26

Chateau™ Direct Vent Gas Fireplace

Attic Installation

Nails (4)

Firestop Spacer

Joist

Ceiling Installation

Joist

Firestop Spacer

Elbow Strap

 

Support Structure

 

 

 

 

Elbow Strap (must be tight)

Ceiling Hole

Framing

Angled Strap

Angled Firestop

Chimney Support Strap (must be tight)

FP270/271

Fig. 38 Attach straps to a structural framing member.

Min.

Nails (4)

Fig. 36 Installing firestop spacer.

Attic

Insulation

Shield

FP593

2' (610mm)

Nails (4 Re- quired)

Attic Joist

 

Base

Ceiling

Flanges

FP263

 

Fig. 37 Attic shield installation.

CFM190

Fig. 39 Minimum termination to roof clearance.

If an attic is above ceiling level an AIS-SK (Attic Insulation Shield) must be installed.

The enlarged ends of the vent section always face downward.

26

20011957

Image 26
Contents INSTALLER/CONSUMER Safety Information What to do if YOU Smell GASTable of Contents Ansi Z21.50b-2005 / CSA 2.22b-2005 Vented Gas Fireplace Installation & Operating InstructionsCertified To Please Review the Following CarefullyGas Equipment Venting System not Provided Requirements for the Commonwealth of MassachusettsClear of ALL Obstructions Locating Your Fireplace Standard FramingClearance to Combustibles MantelsFinal Finishing HearthFraming and Finishing Gas Inlet and Manifold Pressures Gas Line InstallationGas Specifications High ElevationsControl System Installation Control SystemSpecial Feature for Cold Climates Inside view of wireless wall switchIntroduction Hand-Held Remote Control Transmitter Operating InstructionsKey Settings LCD Liquid Crystal DisplayManual Function Thermostat FunctionSetting LOCK-OUT CP Continuous Pilot FeatureCP Childproof Feature Thermostatic Updating Feature Operational NotesGeneral Venting Location of Vent TerminationCanadian Installations1 US Installations2 General Venting Information Termination LocationGeneral Information Assembling Vent Pipes SK8 Venting Pipes Canadian InstallationsUSA Installations Sidewall Applications Horizontal TerminationVertical Termination Sidewall Installation StepAlways install horizontal venting on a level plane Zero clearance sleeve is only required for combustible wallsSidewall Installation with Stationary Glass Facing Outside Horizontal length requirementInstallation Procedure Installing the 38S2VDK DoorFlue Restrictor Plate Guide Flue Restrictor Plate InstallationRestrictor Plate Installation Typical ApplicationsFlue restrictor plate use in straight up installation Vertical Through-the-Roof Installation + 2 + 3 + 4 =Min Chimney Components Component Description Model NumberCeramic Refractory Installation Glass Frame Assembly RemovalGlass Cleaning Clean the glass after the first two weeks of operationLog, Lava Rock and Ember Placement DVT38Sw log identificationLog Pilot Plumbing F50 Overlay is very fragile Log Right Flame Characteristics Trim Installation Turning Off the Gas to the Appliance Lighting & Operating InstructionsLighting Instructions Operation TroubleshootingAmerican Flame Gas Control System Troubleshooting American Flame Gas Control System American Flame Gas Control System Error Codes What to CheckFuel Conversion Instructions Conversion PrecautionsConversion Procedure Remove pilot orifice Valve Minimum Rate Screw Pilot Flame AdjustmentDVT38S2 Injector Orifice Size Matrix Conversion to LPBurner and Burner Compartment MaintenanceCleaning the Control System DVT38S2 Units GFYW5Q0 DVT38S2 DVT38S2Fuel Conversion Kits Wall Mountable Wireless Remote Transmitter AccessoriesBack-up Battery Kit Limited Lifetime Warranty Product Covered by this WarrantyEfficiency Ratings Model EnerGuide Ratings Fireplace Efficiency %