DVS 30-2 DVS-30 Framing and Finishing, Installing Support Brackets Figure

Page 19

DVS-30 FRAMING AND FINISHING

Installing Support Brackets (Figure 29)

A horizontal pipe support MUST BE used for each 3 feet of horizontal run. The pipe supports should be placed around 8 inch diameter pipe and nailed in place to framing members. There MUST BE a 3 inch clearance to combustibles above 6 5/8 inch diameter pipe and elbows and 1 inch clearance on both sides and bottom of 6 5/8 inch pipe to combustibles on all horizontal pipe sections and elbows.

Vertical runs of this vent systems must be supported every 4 feet above the appliance flue outlet by wall brackets attached to the 6 5/8 inch vent pipe and secured with nails or screws to structural framing members.

Figure 29

Installing Firestops (Figures 30, 31, 32 and 33)

Firestops are required for safety whenever the vent system passes through an interior wall, an exterior wall, or a ceiling. These firestops act as a firebreak heat shield and as a means to insure that minimum clearances are maintained to the vent system.

Horizontal runs in the vent system which pass through either interior or exterior walls, require the use of wall firestops on both sides of the wall through which the vent passes.

Position the firestops on both sides of the 10 inch x 10 inch hole, previously cut. Secure with nails or screws. The heat shields of the firestops MUST BE placed towards the top of the hole. Continue the vent run through the firestops. (Figure 30)

Figure 30

Vertical runs of this system which pass through ceilings require the use of ONE (1) ceiling firestop at the hole in each ceiling through which the vent passes.

Position a plumb bob directly over the center of the vertical vent component and mark the ceiling to establish the center point of the vent. Drill a hole or drive a nail through this center point and check the floor above for any obstructions such as wiring or plumbing runs. Reposition the appliance and vent system, if necessary, to accommodate ceiling joists and/or obstructions.

Cut a 10 inch x 10 inch hole through the ceiling, using the center point previously marked. Frame the hole with framing lumber the same size as the ceiling joists. (See Figure 31) If the area above the ceiling is NOT an attic, position and secure the ceiling firestop (SD-963) on the ceiling side of the previously cut and framed hole. (See Figure 32) If the area above the ceiling IS an attic, position and secure the firestop on top of the previously framed hole. (See Figure 33)

NOTE: Remove insulation from the framed area in the attic before installing the firestop and/or vent pipes.

13369-1-0203

Page 19

Image 19
Contents Installation Instructions Table of Contents Important Safety Information LP-GAS Warning Odor Safety Information for Users of LP-GASIntroduction Fireplace Dimensions Model DVS-30/DVS-36/DVS-42 SpecificationsHeater Baffle is Used on DVS-36 & DVS-42 only Fireplace Component InstallationClearances Figure Mantel Chart FigureClearances Locating FireplaceGAS Supply Installing a New Main Gas CockChecking Manifold Pressures Example B InstallationVenting Fireplace Example aVent Runs Figures 14, 15, 16, 17 Three 3 basic types of installationsFraming Figure Finishing FigureInstallation Vertical Sidewall Application Positioning the Fireplace Cutting the Hole Figures 22 MAXTermination Clearances Vertical Sidewall InstallationsInformation on Various Venting Routes and Components Vent Clearances Vent System Identification Installing Vent Components FigureInner flue joints do not require any sealant Installing Firestops Figures 30, 31, 32 Installing Support Brackets FigureDVS-30 Framing and Finishing DVS-30 Framing and Finishing DVS-36 & DVS-42 Framing and Finishing Installing Firestops Figures 35, 36, 37DVS-36 & DVS-42 Framing and Finishing Vertical Termination For All Models Installing the Vent System in a ChaseGlass Removal LOG PlacementReassembly and Resealing Vent Pipe System Vertical Through the Roof Applications FigureTOP View of LOG SET Glass ReplacementDVS-30 Placement of glowing embers DVS-36 and DVS-42 Placement of glowing embersFlame Appearance Standing Pilot Operating InstructionsMillivolt System Figures 48 Recommended Wire Gauges Standing Pilot Wiring Diagram What to do if YOU Smell GAS Standing Pilot Lighting InstructionsGlass soots Standing Pilot TroubleshootingFrequent pilot outage problem Pilot and main burner extinguish while in operationElectrical Connection Figure DVS-36 & DVS-42 Intermittent Pilot Wiring DiagramTo Turn OFF GAS to Appliance Checkout SpecificationsOperation Trial for IgnitionMain Burner Operation Safety LockoutARC Length Action Ignition System ChecksDVS-36 & DVS-42 Intermittent Pilot Troubleshooting RF Standing Pilot Operating Instructions RF Wiring Diagram RF Standing Pilot Lighting Instructions Please Note Maintenance and ServiceDVS-30 Parts List HOW to Order Repair Parts#41 Orifice NAT DVS-36 Parts ListDVS-42 Parts List Parts View Louvers Accessory PartsVariable Speed Blower Installation Instructions Blower Motor FBB1A Blower Installation Optional Single Speed Blower Installation InstructionsParts List Optional Fresh Air Intake Kit Figure Optional Fresh AIR Intake KIT DVFB-AK-30, FB-AK-2Example of Installation DVS-BL-30-2, DVS- BL-36-2, DVS-BL-42-2 Installing Optional Brick LinerParts List Brick Liner KIT