Weil-McLain 80 manual Install jacket, Before installing jacket, Remove jacket parts from cartons

Page 20

Weil-McLain 80 Boiler For Gas, Light Oil, Gas/Light Oil Fired Burners

9 Install jacket

Before installing jacket

1.Packaged boilers

Install top jacket panels per instructions in this manual.

2.Non-packaged boilers

Follow the instructions in this section to install all jacket panels.

Make sure the following are completed before installing jacket:

Boiler hydrostatically pressure-tested. See page 8.

Plugs for unused tappings installed. See control tapping table, page 28 or 29.

Supply and return piping installed. See pages 14 through 19.

Cleanout plates, flue collar and flue collector hood installed. See pages 9 through 13.

3.These parts must be on boiler:

plugs for unused tappings

supply and return piping

steam supply header

cleanout plates

tankless heater(s) (when used)

tankless heater cover plate(s) (when used)

tankless heater piping (when used)

flue damper assembly

flue collector hood

observation port assemblies

4.These parts may be on boiler:

burner mounting plate

burner

5.These parts must be off boiler:

water or steam gauge

limit control

low water cutoff

gauge glass and gauge glass cocks

tri-cocks

drain cock

The boiler contains ceramic fiber and fiberglass materials. Use care when handling these materials per instructions on page 38 of this manual. Failure to comply could result in severe personal injury.

Remove jacket parts from cartons

1.Locate jacket cartons.

2.Remove jacket parts from cartons as needed. Leave in cartons as long as possible to avoid damage.

Install support brackets and rails

1.Place upper and lower support brackets over draw rods as shown in Figure 20, page 21.

2.Fasten securely with 5/8" nuts where shown.

Models 380, 480, 580, 680 and 780 do not require lower support brackets. Only upper brackets are required.

3.Space the brackets along the length of the boiler so there are close to an equal number of sections on either side of the bracket(s).

4.Attach the upper and lower rails on each side of the boiler by securing with #10 x ½" Phillips pan head screws. DO NOT tighten the screws more than finger- tight.

Install jacket front and rear panels

1.Attach the front and rear jacket panels to the upper and lower channels using #10 x ½" Phillips pan head screws, as shown in Figure 20.

2.Rear flue boilers only — remove rear jacket panel flue collector transition knockout with tin snips before installing on boiler.

20

Part No. 550-141-935/0602

Image 20
Contents Boiler Manual Contents Before installing boiler Installation must comply withBefore selecting boiler location Lay a foundation, if neededProvide combustion and ventilation air openings For block assembly Using crane attach free end of cables to eye of craneSet boiler in place For packaged boilerInstall back refractory blanket Assemble blockPrepare back section Place a block under pipe to hold section uprightPrepare remaining sections Install intermediate sectionsIf using tankless heater TI sections Perform hydrostatic pressure test Prepare boiler and testInstall cleanout plates Complete block assemblyInstall burner mounting plate on front section Install flue collector Flue collector assemblyInstall collector hold-down bolts Prepare flue collector hood assemblyInstall flue collector Before installing flue collector After installing flue collector, ALL BoilersRear flue boilers only Top flue boilers onlyInstall flue collector General water piping information Install pipingConnect water boiler piping Piping for multiple boilers see Figure Size secondary boiler pump GPM based on following formulasConnect steam boiler piping General steam piping informationConnect steam boiler piping Condensate piping to boiler Condensate receiver capacity Multiple Steam Boiler Piping Gravity Condensate Return Install jacket Before installing jacketInstall support brackets and rails Install jacket front and rear panelsInstall jacket Install jacket trim Install jacket side panelsInstall jacket top panels Jacket side panel placement Models 380, 480, 580 Jacket side panel placement Models 780, 880 Jacket side panel placement Models 1080, 1180, Jacket top panel placement Size piping no smaller than heater inlet and outlet Pipe tankless heatersTo pipe tankless heaters Install water boiler controls Install controlsInstall steam boiler controls Install controls where shown in and FigureWater level control locations see Table Select type of venting system Connect breeching and venting systemsGeneral venting information Construct metal breeching Make final adjustments Install burnerWiring and fuel piping Freeze protection when used Check boiler for gas-tight sealDimensions and ratings Dimensions and ratings Parts Parts Handling ceramic fiber and fiberglass materials Eye Irrigate immediately Breathing Fresh airPropane boilers propane gas odorant All Residential & Commercial Cast Iron Boilers