Weil-McLain 80 manual Install intermediate sections, Prepare remaining sections

Page 7

• Installation • Start-Up • Maintenance • Parts

3 Assemble block (continued)

Install intermediate sections

Sections are top heavy. Unbolted sections may fall if not supported, resulting in severe personal injury or death.

1.Remove and discard 3/8" diameter shipping tie rods.

2.Remove grit from port machined surfaces with clean rag.

Do not use petroleum-based cleaning or sealing compounds in boiler system. Severe damage to system components can result, causing substantial property damage.

3.Position intermediate section so aligning lugs fit into sockets of next section. See Figure 6.

4.Install TI (tankless intermediate) and SI (supply intermediate) sections (when used) in order shown in Table 3.

5.Draw sections together until metal-to-metal contact is made around machined port openings (see Figure 6):

a.Oil threads on 4 draw rods. Install washer and nut on end to be tightened. Use nut only on other end.

b.Uniformly draw sections together, starting at washer/nut end.

Important Leave an equal amount of thread on each end of the draw rod. This is needed to allow securing the jacket support brackets in place (see pages 20 and 21).

c.Draw rods should be torqued to a range of 90 to 100 ft. - lbs. Do not back off draw rods.

d.Metal-to-metal contact will be achieved around port openings. See Figure 6. If gap occurs, it should be no greater than .032". Check with feeler gauge.

e.If, for any reason, gap around machined port opening exceeds .032", check for rope extending from rope grooves, dirt on port openings or sockets, or misaligned lugs. If corrections are made and gap still exists, contact your Weil-McLain distributor or sales office before continuing installation.

6.

 

After erecting first intermediate section, check both

 

 

 

sections for plumb. Failure to plumb sections can cause

 

 

 

 

misaligned piping and breeching, possibly resulting in

 

 

property damage.

7. Repeat steps 1-5 from “Prepare back section,” page 6.

Install bottom refractory blanket on combustion chamber floor inside section block

1.Unroll blanket only to depth of back section and first intermediate section.

2.Spread adhesive on bottom side of blanket.

3.Press blanket into center bottom of sections.

4.Unroll and install blanket per steps 2 and 3 as each intermediate and front section are installed.

5.At front section, cut off blanket 2 ½" from burner opening. Discard unused blanket.

Figure 6 Sealing ring installation and port alignment

Table 3 Section arrangement

Do not use petroleum-based cleaning or sealing compounds in boiler system. Severe damage to system components can result, causing substantial property damage.

b.Check each section for proper sealing rope position before proceeding to next section.

Failure to position sealing rope properly can cause boiler to not seal gas-tight. Gas tight seal prevents possible flue gas leakage and carbon monoxide emissions, resulting in severe personal injury or death.

Prepare remaining sections

1. Follow “Prepare intermediate section” for remaining intermediate and front

If using tankless heater (TI) sections

 

sections:

1. Install tankless heaters and gaskets or heater cover plates

a. Remove any grit from threads inside tapped holes with clean rag.

and gaskets. Use 3/8" x 3/4" studs, washers and nuts.

Part No. 550-141-935/0602

7

Image 7
Contents Boiler Manual Contents Lay a foundation, if needed Before installing boilerInstallation must comply with Before selecting boiler locationProvide combustion and ventilation air openings For packaged boiler For block assemblyUsing crane attach free end of cables to eye of crane Set boiler in placePlace a block under pipe to hold section upright Install back refractory blanketAssemble block Prepare back sectionIf using tankless heater TI sections Install intermediate sectionsPrepare remaining sections Prepare boiler and test Perform hydrostatic pressure testInstall burner mounting plate on front section Complete block assemblyInstall cleanout plates Prepare flue collector hood assembly Install flue collectorFlue collector assembly Install collector hold-down boltsInstall flue collector Top flue boilers only Before installing flue collectorAfter installing flue collector, ALL Boilers Rear flue boilers onlyInstall flue collector Connect water boiler piping Install pipingGeneral water piping information Size secondary boiler pump GPM based on following formulas Piping for multiple boilers see FigureGeneral steam piping information Connect steam boiler pipingConnect steam boiler piping Condensate piping to boiler Condensate receiver capacity Multiple Steam Boiler Piping Gravity Condensate Return Install jacket front and rear panels Install jacketBefore installing jacket Install support brackets and railsInstall jacket Install jacket top panels Install jacket side panelsInstall jacket trim Jacket side panel placement Models 380, 480, 580 Jacket side panel placement Models 780, 880 Jacket side panel placement Models 1080, 1180, Jacket top panel placement To pipe tankless heaters Pipe tankless heatersSize piping no smaller than heater inlet and outlet Install controls Install water boiler controlsInstall controls where shown in and Figure Install steam boiler controlsWater level control locations see Table General venting information Construct metal breeching Connect breeching and venting systemsSelect type of venting system Wiring and fuel piping Install burnerMake final adjustments Check boiler for gas-tight seal Freeze protection when usedDimensions and ratings Dimensions and ratings Parts Parts Eye Irrigate immediately Breathing Fresh air Handling ceramic fiber and fiberglass materialsPropane boilers propane gas odorant All Residential & Commercial Cast Iron Boilers